Why was Hoang Cau Lake filled up outside the approved plan?

Báo Tiền PhongBáo Tiền Phong19/09/2024


Hanoi

TPO - Currently, Dong Da District People's Committee is implementing the project to synchronously renovate the technical infrastructure of Dong Da Lake urban landscape. However, a part of the lake was filled up, not included in the planning and design, which surprised the people.

Why was Hoang Cau Lake filled up outside the approved plan? Photo 1

From July 2024, the entire Dong Da Lake area (also known as Hoang Cau Lake in Dong Da district) will be fenced to implement the Project of synchronously renovating the technical infrastructure of Dong Da Lake urban landscape.

Why was Hoang Cau Lake filled up outside the approved plan? Photo 2
On October 31, 2023, the Dong Da District People's Council approved the investment policy, assigning the District Construction Investment Project Management Board as the investor. By March 29, 2024, the Dong Da District People's Committee had approved the project with a total investment of more than 297 billion VND. The winning contractor is Vietnam Construction and Import-Export Joint Stock Corporation (VINACONEX).
Why was Hoang Cau Lake filled up outside the approved plan? photo 3

However, many people around the area were extremely surprised when the construction unit leveled and drove piles into the lake bed (Hoang Cau street area), causing the lake surface area to narrow.

Why was Hoang Cau Lake filled up outside the approved plan? photo 4

Thousands of square meters of Dong Da Lake surface were filled, machinery was operating busily.

Why was Hoang Cau Lake filled up outside the approved plan? Photo 5

Notably, there are areas that are not in the perspective that have also been filled in. In the photo is the lake section adjacent to lane 38 Hoang Cau which is not in the perspective.

Why was Hoang Cau Lake filled up outside the approved plan? Photo 6

Perspective of Dong Da Lake renovation was announced earlier.

Why was Hoang Cau Lake filled up outside the approved plan? Photo 7

Dong Da Lake Peninsula is also fenced with piles for expansion purposes. Dong Da Lake Peninsula was originally planned to implement the "Investment project to renovate and upgrade Dong Da Lake Peninsula entertainment area" with the expectation of becoming an entertainment area, serving the spiritual life of local residents. In 2010, Hanoi granted an investment certificate to Ha Thuy Development Investment Joint Stock Company to implement the project on a land area of ​​over 5,600m2 with a lease term of 50 years.

Why was Hoang Cau Lake filled in outside the approved plan? Photo 8
Informing the press, Vinaconex Corporation (construction contractor) admitted to the above-mentioned leveling activities.
Why was Hoang Cau Lake filled up outside the approved plan? Photo 9

The project contractor said that the embankment area is part of the construction method design to serve as a staging area for construction machinery and equipment and a temporary road for pile driving and construction of a walking path around the lake.

Why was Hoang Cau Lake filled up outside the approved plan? Photo 10

This unit affirmed: After completing the construction of the walkway structure, the contractor will proceed to dispose of this material according to regulations.

Why was Hoang Cau Lake filled up outside the approved plan? Photo 11
It is known that Dong Da Lake has an area of ​​about 13.3 hectares. To the East and Southeast is Hoang Cau Street connecting Lang Street to De La Thanh Street, passing through and running around the lake is Dang Tien Dong - Mai Anh Tuan Street. The streets around Dong Da Lake have a length of 1,270m with a current cross-section of 6.5m.
Why was Hoang Cau Lake filled up outside the approved plan? Photo 12

It is expected that after renovation and upgrading, Dong Da Lake will become spacious, clean and beautiful with modern architecture, in sync with existing works.

Why was Hoang Cau Lake filled up outside the approved plan? Photo 13

The representative of Dong Da District People's Committee added that the project will renovate, expand and upgrade the walking path below on the basis of the existing embankment with rough natural stone surface. Replace the degraded and damaged railing system around the lake. Plant new trees and replace some shade trees that are rotten, leaning, broken, and not of the urban tree type; arrange a system of carpet trees and decorative shrubs interspersed with the seating system and walking path along the lake...

Why was Hoang Cau Lake filled up outside the approved plan? Photo 14

The backfill area is not included in the design perspective.

Tran Hoang



Source: https://tienphong.vn/vi-sao-ho-hoang-cau-bi-san-lap-ngoai-quy-hoach-duoc-duet-post1674614.tpo

Comment (0)

No data
No data

Same tag

Same category

Colorful Vietnamese landscapes through the lens of photographer Khanh Phan
Vietnam calls for peaceful resolution of conflict in Ukraine
Developing community tourism in Ha Giang: When endogenous culture acts as an economic "lever"
French father brings daughter back to Vietnam to find mother: Unbelievable DNA results after 1 day

Same author

Image

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product