Permanent Deputy Prime Minister Nguyen Hoa Binh directed to complete site clearance for the Hoa Lien - Tuy Loan expressway (Da Nang City) in March, prioritizing the supply of stone for project construction.
Increase construction speed to compensate for progress
On the morning of March 13, the Government's Inspection Team No. 1, led by Permanent Deputy Prime Minister Nguyen Hoa Binh, inspected the construction status of the Hoa Lien - Tuy Loan expressway project.
Deputy Minister of Construction Nguyen Viet Hung, representatives of the Ministry of National Defense, Da Nang City People's Committee... participated in the Government's inspection delegation.
Representative of Ho Chi Minh Road Project Management Board reported to the Inspection Team on the construction status of Hoa Lien - Tuy Loan Expressway.
Reporting to Permanent Deputy Prime Minister Nguyen Hoa Binh, a representative of the Ho Chi Minh Road Project Management Board said that the main route of the expressway project has no land clearance problems, and the two service roads still have some unsolved documents.
The expressway project has 1 construction package, the total value of which has been implemented to date is 374/859.58 billion VND, reaching 43.5% of the contract value. This construction progress is about 0.8% behind schedule.
According to records on the morning of March 13, machinery and workers were busy working along the highway. Most of the road surface items have been and are being constructed, many locations have reached the C19 asphalt concrete stage.
According to the Ho Chi Minh Road Project Management Board, after the Lunar New Year, contractors increased human resources and equipment, added 5 construction teams, organized overtime, and simultaneously deployed construction teams for the foundation, road surface, etc. to basically meet the construction schedule.
The contractor is determined to shorten the progress, basically completing it in August 2025 in accordance with the Prime Minister's direction.
A representative of the contractor, Truong Son Construction Corporation, said that the unit arranged 19 construction teams with hundreds of workers and machines to work continuously. When the site and materials are available, the contractor strives to work day and night to meet the project's progress.
Hoa Lien - Tuy Loan expressway construction site is busy when the weather is favorable.
Priority is given to providing 200,000m3 of available stone for the project.
Mr. Le Thanh Binh, Deputy Director of the Ho Chi Minh Road Project Management Board, informed that currently, the highway's frontage road surface is still about 0.57km long, lacking the source of stone materials to supply for the project.
The project needs about 200,000m3 of stone, but the mines in Da Nang can currently supply 70,000m3. It is recommended that the Da Nang People's Committee direct the early increase of the capacity of Truong Ban quarry to serve the project.
Next to that, a mine in Da Son (Hoa Khanh Nam ward, Lien Chieu district, Da Nang city) has 600,000m3 of finished stone but cannot be purchased due to procedural problems.
According to Mr. Phan Van Ton, Chairman of Hoa Vang District People's Committee, the locality is trying to complete site clearance for the entire frontage road in March to hand over for construction.
The main highway route is no longer stuck with site clearance, the contractor has increased the construction to meet the project schedule.
Deputy Prime Minister Nguyen Hoa Binh assessed that the capacity increase of quarries to serve the Hoa Lien - Tuy Loan expressway project is still slow compared to the Prime Minister's direction (at the project inspection in September 2024).
According to the Permanent Deputy Prime Minister, the Da Son quarry currently has 600,000m3 of rock available, while the project needs 200,000m3. He directed Da Nang and related units to work together, prioritizing the provision of 200,000m3 of available rock for the project, as waiting for procedures to increase the capacity of other quarries would take a long time.
Permanent Deputy Prime Minister Nguyen Hoa Binh also directed the locality to try to mobilize people to hand over the land, with March 29 as the deadline to complete this work, towards celebrating the 50th anniversary of Da Nang's liberation.
The Hoa Lien - Tuy Loan Expressway project is 11.47km long, passing through Hoa Lien, Hoa Nhon, and Hoa Son communes of Hoa Vang district, Da Nang city. The total investment of the project is over 2,100 billion VND.
The project is invested by the Ho Chi Minh Road Project Management Board, starting in September 2023, completed according to the contract in November 2025; expected to shorten the completion of the expressway to August 2025.
The project has 1 construction package constructed by the Joint Venture of Truong Son Construction Corporation - CTGT 5-CTCP Construction Corporation - 17 LLC.