Although the disbursement results of public investment capital in the first 9 months of the year have not reached the set plan, with many new projects starting construction and some difficulties being resolved, Quang Yen Town is focusing on speeding up the progress of construction projects to ensure the volume and disbursement of assigned capital.

In 2024, Quang Yen Town was assigned a total adjusted public investment capital of more than 714 billion VND from the provincial budget, new rural capital and local budget. Implementing the province's direction in disbursing public investment capital, Quang Yen Town requested the construction units of transitional works to mobilize human resources and equipment to ensure continuous construction, and at the same time requested the units, departments and units assigned as investors to complete the procedures and documents to ensure the commencement of projects in the list. By the end of September, the projects in the list of new works to start construction according to the plan at the beginning of the year had all been organized for construction.
The resettlement area project serving projects in Quang Yen town in Phong Hai ward, phase 2, is one of the new projects that started construction at the end of September. To ensure the project's construction progress, the contractor has mobilized human resources and equipment to speed up the items. Currently, the disbursement of capital has reached over 5.5 billion VND out of the total 34 billion VND allocated for the project in 2024.

Mr. Tran Ngoc Duy, Deputy Director of Hai Ninh Construction Joint Stock Company, the contractor participating in the project, said: Although the construction has just been organized, the unit has arranged human resources and about 50 equipment and vehicles to transport soil and rock to level the resettlement area. Currently, the leveling has reached about 30% of the total project area. Taking advantage of favorable weather conditions, the unit is accelerating the construction of technical infrastructure items of the project. Thereby, ensuring the workload of disbursing the capital that the town has allocated for the project in 2024.
By focusing on removing difficulties in investment preparation and organizing construction of projects, after 9 months, Quang Yen Town has disbursed over 224 billion VND, reaching nearly 32% of the adjusted capital plan and over 50% of the allocated capital.

Mr. Bui Van Tan, Director of the Quang Yen Town Construction Investment Project Management Board, said: In addition to the regular difficulties, 2024 is the first year of applying the amended Bidding Law and the Land Law, which has impacted and affected the investment preparation and site clearance work for construction projects, so the disbursement results of public investment capital in the first 9 months of the year have not been guaranteed compared to the set plan. Currently, the Project Management Board has advised and reported to the town to focus on resolving some problems with the site of some remaining project works to hand over to the construction contractor. At the same time, increase human resources and equipment, add more construction teams day and night in the last months of the year to ensure the volume of disbursement of the assigned capital.