Package 2 started later than other packages along the route, so to keep up with the overall progress, the contractor arranged 13 construction teams divided into 20 construction groups across the entire package.
Due to the complex terrain, each column location requires a suitable construction plan, both ensuring technical requirements and minimizing the impact on residential and production land of local people.

Mr. Nguyen The Hien, Commander of Package No. 2, Power Construction One Member Co., Ltd. 4 said: One of the current difficulties is the large volume of excavation and filling, many locations are stuck with rocks, bringing vehicles to the construction site is very difficult, so we have to calculate many construction plans to ensure progress and safety. To facilitate the construction process, we have worked with local authorities, announced the time and construction plan so that people in the area can understand. Currently, the authorities and people in the area are enthusiastically supporting the project construction.

Package No. 2, Lao Cai - Vinh Yen 500kV transmission line project, construction from pole 53 to pole 99, passing through Bao Yen district. The construction unit strives to complete the foundation construction before June 10, pole construction by July 15 and wire pulling by August 31.
Source: https://baolaocai.vn/trien-khai-thi-cong-du-an-duong-day-500kv-lao-cai-vinh-yen-doan-qua-huyen-bao-yen-post399797.html