Ho Chi Minh City still has more than 30,000 billion VND of land clearance capital that has not been disbursed.

Báo Đầu tưBáo Đầu tư21/08/2024


Ho Chi Minh City still has more than 30,000 billion VND of land clearance capital that has not been disbursed.

By the end of July 2024, Ho Chi Minh City had disbursed VND 2,440 billion in land clearance capital, the remaining VND 30,234 billion had not been disbursed due to the impact of the new Land Law, so it had to be adjusted.

The Department of Planning and Investment has just reported to the Ho Chi Minh City People's Committee on the results of public investment disbursement in the first 7 months of the year and solutions for disbursement in the remaining months of 2024.

Xuyen Tam canal renovation project increases land clearance capital by 7,600 billion VND - Photo: Trong Tin

According to the report, as of August 2, 2024, the total disbursed public investment capital of the City was VND 12,064 billion, reaching 15.2% of the total public investment capital assigned by the Prime Minister in 2024, which is VND 79,263 billion.

This year, Ho Chi Minh City allocated VND32,674 billion for site clearance, but by the end of July, only VND2,440 billion had been disbursed. The remaining VND30,234 billion had not been disbursed due to the change in the Land Law, which took effect earlier.

Therefore, from August 1, State management agencies must supplement compensation regulations according to the new Land Law to add a number of new policies that are more beneficial to the people to facilitate the process of site clearance.

Therefore, the procedures for compensation and site clearance are slow, leading to slow disbursement of public investment capital.

Many projects that had previously had their total investment approved, when implementing and applying the provisions of the new Land Law from August 1, the total investment increased due to increased compensation capital for site clearance.

A typical example is the Project to dredge and improve the environment for infrastructure construction of Xuyen Tam canal (from Nhieu Loc Thi Nghe canal to Vam Thuat river). When applying the new Land Law regulations, the total estimated cost of compensation and site clearance is up to VND 12,978 billion (an increase of VND 7,600 billion compared to the previously approved cost).

The next project with increased land clearance capital is the Project of Dredging, Infrastructure Construction, and Environmental Improvement of the North Bank of Doi Canal (District 8), with land clearance capital of up to VND 5,100 billion (an increase of VND 2,400 billion compared to the previously approved cost).

In addition, Ho Chi Minh City has a number of projects with very large land clearance capital such as: Ring Road 2 project (section from Phu Huu bridge to Vo Nguyen Giap street) is 6,600 billion VND; section from Vo Nguyen Giap street to Pham Van Dong street is 1,800 billion VND.

To disburse the remaining capital of more than VND 30,000 billion, the Department of Planning and Investment proposed that the Ho Chi Minh City People's Committee assign specialized departments to coordinate with investors and localities to prepare documents to propose adjustments to the investment policy for the People's Committee to submit to the City People's Council at a special session in September 2024.



Source: https://baodautu.vn/tphcm-con-hon-30000-ty-dong-von-giai-phong-mat-bang-chua-giai-ngan-duoc-d222833.html

Comment (0)

No data
No data

Same tag

Same category

Son Doong Cave is among the top 'surreal' destinations like on another planet
Wind power field in Ninh Thuan: Check-in "coordinates" for summer hearts
Legend of Father Elephant Rock and Mother Elephant Rock in Dak Lak
View of Nha Trang beach city from above

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product