Attending the event were Ms. Truong Thi Bich Hanh, Standing Member of the Provincial Party Committee, Secretary of the Di An City Party Committee, along with city leaders, departments and representatives of wards.
Binh Thang Secondary School is built on a land area of 19,613.4m2; total construction floor area of 14,528.9m2; belonging to a secondary education project divided into 5 building blocks with 4 floors and 1 attic, including: Administrative block, study services and classrooms, subject classrooms; Lunch break block, Canteen combined with multi-purpose gym, kitchen with 4 floors and 1 technical floor; Parking block, Gym and auxiliary items. The project is expected to be built in 600 days with a cost of more than 130 billion VND.
Route D9 (from Le Van Mam to Nguyen Thi Minh Khai) was inaugurated with a length of 173.77 m; it was completely built, synchronously with lighting items, trees, low-voltage power lines, traffic signs, and lane dividers to ensure traffic safety.
The project was built in 270 days with a construction cost of more than 4 billion 824 million VND.
The project to upgrade and expand Nguyen Khuyen Primary School was carried out on a land area of 7,292.40 m2, with the newly built part including: Classrooms, functional rooms, serving learning and administrative management; renovating and upgrading the 3-storey and 4-storey blocks, kitchen - dining room combined with multi-purpose house.
The project was constructed in 420 days with a construction cost of more than 38 billion 240 million VND.