Many problems need to be solved
Implementing Decision No. 809/QD-UBND dated March 20, 2025 of the Provincial People's Committee on the establishment of a Working Group to urge the handling of backlogs in compensation and resettlement support for hydropower projects in the province, on April 10 and 11, a working delegation led by Mr. Pham Van Hoa - Director of the Department of Industry and Trade, together with representatives of a number of provincial departments and branches, made a trip to inspect and work with leaders of Que Phong, Tuong Duong, and Thanh Chuong districts to resolve problems at the hydropower projects: Hua Na, Ban Ve, and Khe Bo.
.jpg)
In Que Phong, on the afternoon of April 10, the delegation worked with the People's Committee of Que Phong district on problems at Hua Na Hydropower Plant.
The Hua Na Hydropower Project has been implemented since 2008. Along with the construction of the Hua Na Hydropower Plant, there is resettlement work for people in Thong Thu, Dong Van and Tien Phong communes of Que Phong district to have new places to live, ensuring stable life and production development.
.jpg)
However, there are still some problems related to handling the difference in land value between the departure and destination places, of which there are currently 251 households that have not approved the deduction plan, of which 41 households have residential land and 210 households have agricultural land.

Land allocation and dossier preparation for granting agricultural land use right certificates in some areas are still difficult and problematic, such as: Issues related to the allocation of agricultural land for growing other annual crops; the allocation of wet rice land has left 46/89 households not yet received project fields; the issuance of forestry land use right certificates has left 77/879 resettled households not yet granted forestry land use right certificates.
In Tuong Duong district, the Working Group inspected the field, worked with the district, commune and investor on difficulties and problems related to resettlement of Ban Ve Hydropower Project and Khe Bo Hydropower Project.

For the Ban Ve Hydropower Project, there are some contents such as: People in the affected area requesting support arising from the project's regulations and support to overcome the flood in 2018; handling land above the flood level of the Ban Ve Hydropower Project; handing over the construction site after the contractors have withdrawn; preparing compensation records for the difference in land value between the departure and destination places for the part below the flood level in the old villages in the reservoir area; and compensation for the difference in land value between the departure and destination places for households subject to concentrated resettlement in Thanh Chuong; preparing compensation records for land in Con Phen village (Huu Khuong commune); Issuing land use right certificates in the resettlement area of Ca Moong village (Luong Minh commune)...

For Khe Bo Hydropower Project, after the reservoir is filled with water, in addition to households whose land is completely affected and must be relocated to concentrated resettlement areas, there are also 398 plots of land of 398 households whose land is partially flooded by the reservoir, so the land records need to be adjusted. However, the adjustment of land records is facing many difficulties. In addition, there are 44 households affected by the reservoir border, so the boundary of the reservoir must be adjusted, leading to the increase and decrease of the area, which requires a solution...
In addition, the compensation and resettlement work of the Khe Bo Hydropower Project has been basically completed, but the final settlement of costs for the compensation and resettlement component submitted to the competent authority for approval has not been carried out.

Urgently resolve before district level ceases operations
Compared to other districts, in Thanh Chuong - where people migrated to, there are currently a number of constructions located in Thanh Son and Ngoc Lam communes such as: market, martyrs' memorial, football field, which need to be reviewed to be suitable for the arrangement of local government apparatus at commune level in the coming time.
At the working sessions, representatives of local authorities and investors of hydropower projects also raised difficulties and obstacles that need to be resolved in order to completely resolve the backlog that has existed for many years.
In order to urge the progress with localities and investors of the above hydropower projects, comrade Pham Van Hoa requested that local authorities at district and commune levels and related units need to set a time frame to completely resolve the problems.

Comrade Pham Van Hoa also emphasized that immediately after these working sessions, the Working Group will have a report to advise the Provincial People's Committee to issue an official directive document. However, he requested that local authorities and related units focus on resolving problems immediately, without waiting for the directive document. Focus on completing the implementation before the district level ceases operations on July 1, 2025.
Source: https://baonghean.vn/to-cong-tac-cua-ubnd-tinh-de-nghi-giai-quyet-dut-diem-nhung-ton-dong-tai-cac-du-an-thuy-dien-10294916.html