According to the report of the Provincial Traffic Construction Investment Project Management Board, as of April 7, 2025, the disbursement rate of public investment capital for key traffic works in the province was VND 265,154 million, reaching 1.17% of the annual plan. Of which, the Ho Chi Minh City Ring Road 3 project has disbursed VND 155,843 million, reaching 5.5%. Up to now, an area of 78.39/79.91 hectares has been recovered, reaching 98.1%; compensation plan of VND 8,380,933 billion/2,893 records has been approved; compensation of VND 8,080,605 billion/VND 8,380,933 billion has been paid, reaching 96.4%; Received handover of site to implement packages of 78.4 hectares / 79.91 hectares , reaching 98%.
Overview of the meeting
For Ho Chi Minh City Ring Road 4, the Provincial People's Committee has approved the land clearance boundary. The land clearance markers have been handed over for 28km/28km, reaching 100%.
For the Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway, the Feasibility Study Report has been approved; 10.8 hectares of Phuoc Hoa rubber land has been handed over to the construction unit.
Mr. Tran Hung Viet - Director of the Provincial Traffic Construction Investment Project Management Board reported on the implementation status of the projects.
Mr. Nguyen Thanh Tam - Chairman of Thuan An City People's Committee reported on difficulties and obstacles in the construction of projects through Thuan An area.
The meeting also heard reports on the implementation of investment preparation projects: The Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway section from Doc Lap intersection to the Ho Chi Minh City border; upgrading and expanding An Binh road and connecting Song Than overpass; Song Than intersection; construction of Hieu Liem bridge; construction of Saigon riverside road from Ba Lua canal to An Son port; construction of railway from Bau Bang station to An Binh station. At the same time, heard reports on the implementation of key projects of the province: Thu Bien - Dat Cuoc road clearance project; Bac Tan Uyen - Phu Giao - Bau Bang force-generating road clearance project; compensation, site clearance, support and resettlement of My Phuoc - Tan Van road project; construction of underpass at Phuoc Kien intersection; upgrading and expanding DT.746 road from Tan Thanh intersection to Hoi Nghia intersection; Upgrading and expanding DT.748 road (section from Phu Thu intersection to My Phuoc town's Northern Ring Road); upgrading and expanding the road from Binh Chuan intersection to the intersection with Tan Phuoc Khanh Martyr Memorial road; building a drainage system on DT.744 road through An Tay ward, Phu An commune; building a bridge across Dong Nai river (Bach Dang 2 bridge).
Vice Chairman of the Provincial People's Committee Bui Minh Tri delivered a concluding speech at the meeting.
Through the opinions of units and localities, Vice Chairman of the Provincial People's Committee Bui Minh Tri requested investors to coordinate with localities to review difficulties and obstacles in implementing projects; propose to the Provincial People's Committee solutions to remove difficulties and obstacles to speed up the construction progress of projects.