Progress of the urban area of ​​over 11,000 billion of the Sun Group joint venture in Binh Thuan

Báo Dân tríBáo Dân trí23/01/2025

(Dan Tri) - According to the project investor's report, the construction investment implementation phase will be completed within 48 months from the date of issuance of the construction permit.


Phan Thiet Sun Investment and Development Company Limited has just released a report related to the new Ham Tien - Mui Ne commercial and service urban area project (area III).

According to the report, the project is implemented on a 218.65-hectare land area in Phu Hai, Ham Tien wards and Thien Nghiep commune (Phan Thiet city, Binh Thuan province), with a scale of 15,000 people.

The North borders the agricultural and forestry land in Thien Nghiep commune, Phan Thiet city; the South borders the current agricultural land, Sao Mai mineral mud project, Ham Tien ward, Phan Thiet city; the Southwest borders the Sealink Mui Ne - Vietnam area, Phan Thiet city; the Southeast borders Vo Nguyen Giap street, Ham Tien ward, Phan Thiet city.

Regarding the current land use status of the project, there is nearly 217.3 hectares of agricultural land; nearly 1.2 hectares of traffic land; the rest is cemetery land and houses on agricultural land. The total investment capital of the project is 11,071 billion VND.

The project's objective is to invest in building a new urban area to serve the local socio-economic development with individual housing areas, townhouses combined with mixed-use commercial services, apartments (if any), social housing, etc.; accommodation service buildings, hotels for real estate business, land use rights owned, used or leased.

Tiến độ khu đô thị hơn 11.000 tỷ của liên danh Sun Group tại Bình Thuận - 1

A corner of Phan Thiet City, Binh Thuan (Photo: N.Lan).

Regarding products, the project invested in building 2,291 social housing units (20% of residential land area); 3,244 commercial housing units, residential land; commercial service works; public works (education, healthcare, culture - sports); other public works.

Regarding the project implementation progress, the investment preparation phase, implementation of legal procedures for investment preparation (including selecting investors, preparing and approving detailed planning at a scale of 1/500,...) must be completed within 12 months from the date of approval of the project investment policy decision.

Compensation, site clearance and land procedures implementation phase, implementation of compensation, site clearance and land procedures are completed within 24 months from the date of completion of investment preparation procedures. Investment implementation phase, implementation of legal procedures related to construction licensing are completed within 24 months from the date of completion of compensation, site clearance and land allocation procedures.

The investment and construction implementation phase is completed within 48 months from the date of issuance of the construction permit. The acceptance and handover phase to the competent authorities, carrying out procedures related to acceptance and handover of the completed construction work is completed within 12 months from the completion of the investment and construction work.

In December 2024, the People's Committee of Binh Thuan province issued Decision No. 2158 approving the consortium of Phu Quoc Beautiful Sea Investment Company Limited and Ha Long Sun Company Limited as investors in the new commercial and service urban area of ​​Ham Tien - Mui Ne (area III).

This is also the only investor registered to implement this project, according to the results of opening the dossier of the Department of Planning and Investment of Binh Thuan province in August 2024.

The above joint venture has established Phan Thiet Sun Investment and Development Company Limited with equity capital of over VND 1,811 billion to implement the Ham Tien - Mui Ne project (zone III). In which, Phu Quoc Beautiful Sea Company contributed 60.4% of the capital, the remaining capital was contributed by Ha Long Sun Company.

Phu Quoc Beautiful Sea Investment Company Limited was established in May 2015, headquartered in An Thoi Ward, Phu Quoc City, Kien Giang. The company is known as the investor of the Bai Sao Complex Tourism Project in Phu Quoc.

Sun Ha Long Company Limited is also the investor of the Sunworld Ha Long entertainment complex project in Quang Ninh province. This enterprise was established in August 2014, headquartered in Bai Chay ward, Ha Long city, Quang Ninh.



Source: https://dantri.com.vn/bat-dong-san/tien-do-khu-do-thi-hon-11000-ty-cua-lien-danh-sun-group-tai-binh-thuan-20250122053109493.htm

Comment (0)

No data
No data

Cùng chủ đề

Cùng chuyên mục

Cùng tác giả

Happy VietNam

Tác phẩm Ngày hè

No videos available