Carry out site clearance for the next phase of My Thuy Port project
My Thuy International Port Joint Stock Company has begun coordinating the implementation of procedures related to site clearance for phase 2-3 of the My Thuy Port Area project.
Mr. Pham Ngoc Minh, Head of the Quang Tri Economic Zone Management Board, said that after restarting the project on March 25, 2024, the contractor has completed the construction of the eastern breakwater and embankment (D.1); storage yard, casting yard, traffic road (2.36 ha); and blocks classified as 1A, 1B, 2B, 2A of the temporary wharf. At the same time, other items such as breakwater, weighing station, concrete mixing station, road, yard, well, etc. are still being implemented to ensure progress.
The My Thuy Port Project items are ensuring progress after the project was restarted in March 2024. Photo: MTIP |
Regarding legal procedures, the project has so far completed many related procedures such as: Detailed construction planning; land use planning and planning; approval of basic design, approval of project feasibility study report (F/S); approval of technical construction design; handover of sea area; granting construction permit for phase 1 of about 320 m of the western breakwater; removing the project from the national mineral reserve area; changing the purpose of forest use. The plan to dredge the water area and turning basin has been agreed upon by the Ministry of Transport in Official Dispatch No. 2059/BGTVT-KCHT dated February 28, 2024.
According to Mr. Pham Ngoc Minh, the total area of land handed over and the decision to reclaim land of the My Thuy Port Area project (phase 1) is 132.82 ha/133.67 ha (the remaining 0.85 ha is undergoing site clearance procedures); Hai Lang District People's Committee has also approved the budget, compensation and support plan and payment to households and individuals with a total amount of 138.2 billion VND.
Regarding land lease procedures, MTIP has been leased land by the People's Committee of Quang Tri province for the first phase with a lease area of 104.7 hectares. With the project's expansion area for phase 1 being 43.44 hectares, the Provincial People's Committee has approved the land use plan for 2024. At the same time, MTIP has hired a surveying consultant to complete the dossier and submit it to the People's Committee of Hai Lang district to notify land recovery and carry out site clearance work.
“Regarding the site clearance for phase 2 and phase 3 of the project (149.09 hectares), the People's Committee of Quang Tri province has approved the supplementary land use plan for 2024 of Hai Lang district. In addition, MTIP is also coordinating with relevant departments and agencies to carry out procedures related to the location of dumping dredged material and the use of dredged material for this project,” Mr. Minh added.
Scene of My Thuy Port Area. Photo: MTIP |
The My Thuy Port Project was approved by the Prime Minister in Decision No. 16/QD-TTg dated January 4, 2019. The project is invested by My Thuy International Port Joint Stock Company (MTIP) with a scale of 10 berths, capable of receiving ships of up to 100,000 DWT, with a total investment of VND 14,234 billion; implementation progress from 2018-2035. In phase 1, the project has a scale of 4 berths, a total investment of VND 5,902 billion; implementation period 2024 - 2026.
Comment (0)