Prime Minister Pham Minh Chinh directed units to construct the Khanh Hoa-Buon Ma Thuot Expressway Project.
In the morning, when inspecting the Van Phong-Nha Trang Expressway Project, the Prime Minister welcomed the contractors and supervision consultants for learning from experience to adjust the progress; requested to promote the good aspects that have been achieved; and highly appreciated the spirit of working through holidays and days off for the development of the country's transport infrastructure.
The Prime Minister proposed to shorten the progress to April 30, 2025 to complete the project. According to the Prime Minister, the units need to take advantage of the dry season weather to speed up the construction progress, especially the leveling item.
Regarding site clearance for the project, the Prime Minister requested that it be completed because there is only one household that has not been relocated in this project; regarding technical infrastructure, the Government will direct, and the locality must also take part. If there are only a few 220kV transmission poles crossing the road, it can still be resolved quickly.
The Prime Minister requested that during the project implementation, attention must be paid to combating negativity, not selling or dividing the bid package for profit; the Ministry of Transport must carefully review this issue, especially ensuring that the project contractor has capacity and experience.
Construction site of Van Phong-Nha Trang Expressway Project.
The Prime Minister requested investors and construction units to reschedule the construction progress, work in "3 shifts, 4 shifts", "eat and sleep quickly", "only discuss work, no backtracking"; if any contractor does well, they will be assigned to the next projects.
The Prime Minister stated that speeding up the progress will benefit the project, reduce costs, and serve the people soon.
Prime Minister Pham Minh Chinh directed the progress of the Van Phong-Nha Trang Expressway Project.
The Prime Minister requested the Vietnam Electricity Group (EVN) to study the mobilization of steel poles, insulators, etc. to relocate cross-cutting power projects. Localities should study the most effective exploitation of intersections to create new development space. The Ministry of Transport must be flexible in this matter, encouraging localities to use their own funds to build more intersections because doing so right when the expressway section is under construction will be more convenient.
Prime Minister Pham Minh Chinh visits an officer working on the roadbed of the Van Phong-Nha Trang Expressway Project.
At the construction site, contractor Lizen reported to the Prime Minister that it is making efforts to shorten the 6-month plan, is ready to support other units; focuses resources, and closely coordinates with local authorities.
Prime Minister Pham Minh Chinh visits a worker laying the roadbed of the Van Phong-Nha Trang Expressway Project.
Reporting to the Prime Minister, the leader of the Ministry of Transport said that they are closely coordinating with Khanh Hoa province to resolve the issue of site clearance, resolve the critical progress, and rebuild the progress in accordance with the situation.
Khanh Hoa province leaders pledged to the Prime Minister to resolve the issue of site clearance this May to ensure the construction of the project...
Prime Minister Pham Minh Chinh visits a road roller driver working on the Van Phong-Nha Trang Expressway Project.
The Van Phong-Nha Trang Expressway Project has a total route length of 83.35km; passing through 4 districts and towns: Van Ninh, Ninh Hoa, Dien Khanh and Khanh Vinh in Khanh Hoa province; Total investment: 11,808 billion VND; construction started: January 2023, completion: according to the contract in December 2025.
The project includes 2 construction packages: (1) Package XL.01: Value of 4,179 billion VND, joint venture of contractors Lizen (leading), Phuong Thanh, Hai Dang and VNCN E&C; (2) Package XL.02: Value of 2,959 billion VND, joint venture of contractors Son Hai (leading), Vinaconex.
The contractors mobilized 42/42 construction sites (24 road sites, 18 bridge sites) with 1,020/657 equipment, 1,877/1,626 workers simultaneously on the entire route. Cumulative output: 3,451/7,138 billion VND, reaching 50% of the contract value, exceeding the contract plan by 5%. The output of each contractor basically exceeded the schedule.
Right from the beginning of the project, with the strong direction of the Government, the Ministry of Transport and Project Management Board 7, the project contractors are all strong and professional contractors who have proactively focused on finding and handling problems regarding construction materials immediately. The contractors have proactively produced, ordered and transported materials and supplies to avoid shortages and price pressures. The contractors have proactively focused on equipment and human resources, speeding up the progress of 3 shifts and 4 teams during the dry season, so the project's output to date has exceeded the contract plan by about 5%...
* Visiting the construction site of the Khanh Hoa-Buon Ma Thuot Expressway Project Phase 1, the Prime Minister highly appreciated the significance of the project and wished to speed up the project's progress; hoped that localities would speed up site clearance work; hoped that contractors and units would work in "3 shifts, 4 shifts", "eat quickly, sleep quickly", "only discuss work, no backtracking".
Prime Minister Pham Minh Chinh visited construction units at the Khanh Hoa-Buon Ma Thuot Expressway Project, Phase 1.
The Prime Minister was pleased to see that despite the hot weather, the staff and workers worked tirelessly.
The Prime Minister hopes that investors, project management boards, and units will promote the spirit of serving the country and people, closely follow progress, comply with quality, technical, aesthetic, environmental sanitation, and labor safety requirements, and avoid negative phenomena.
Prime Minister Pham Minh Chinh listened to a report on the Khanh Hoa-Buon Ma Thuot Expressway Project.
The Prime Minister stated that, through discussions, the issue of site clearance emerged, so the two provinces of Dak Lak and Khanh Hoa must take the initiative to intervene and encourage on-site resettlement for people; this work must be done quickly while ensuring that the lives of people relocated to new places are equal to or better than their old places; this work must be done before May 30 and June 30, 2024, according to the recommendations of the investor and contractor.
Prime Minister Pham Minh Chinh listens to an introduction to the Van Phong-Nha Trang Expressway Project.
The Prime Minister requested that during the process, a comprehensive plan must be put in place to invest in the intersection between this expressway project and National Highway 26 to create more convenience for Khanh Hoa and the people; the Ministry of Transport and Khanh Hoa province must work on this issue. According to the Prime Minister, having more intersections will make things more convenient.
The Prime Minister requested that the process must control progress, shorten time, ensure quality, and use "3 shifts, 4 crews" to construct, and at the same time resolutely handle contractors who do not perform well.
Prime Minister Pham Minh Chinh presented gifts to encourage units constructing the Van Phong-Nha Trang Expressway Project.
The Khanh Hoa-Buon Ma Thuot Expressway Project has a total length of 117.5km, passing through Khanh Hoa province (about 32.7km) and Dak Lak province (about 84.8km) with a scale of 4 lanes, divided into 3 component projects including: DATP 1 has a length of 32.0km, with the People's Committee of Khanh Hoa province as the managing agency. The total investment of 5,333 billion VND includes 2 construction packages.
DATP 2 is 37.5km long, with the Ministry of Transport as the managing agency (Project Management Board 6 is the investor). The total investment is 10,436 billion VND, including 3 construction packages. DATP 3 is 48.0km long, with the People's Committee of Dak Lak province as the managing agency. The total investment is 6,165 billion VND, including 3 construction packages. Implementation time: Investment preparation work in 2022, basically completing some sections with high traffic volume in 2025, basically completing the entire route in 2026 and completing the synchronous operation of the entire project in 2027. Regarding construction work, the accumulated output to date is 684 billion / 17,033 billion VND, reaching about 4% of the contract value, basically following the project progress...
Source