Speaking at the meeting on the afternoon of December 6, Prime Minister Pham Minh Chinh pointed out that, in parallel with completing the project on schedule, the quality must ensure environmental safety and technical and aesthetic standards, and it must be noted that bidding must not be used as a "safe haven" for the green and red armies.
Also attending were Deputy Prime Minister Tran Hong Ha, Minister of Transport Tran Hong Minh, Minister of Construction Nguyen Thanh Nghi, Minister and Head of the Government Office Tran Van Son, and leaders of ministries and localities where projects are being implemented.
The Prime Minister chaired the 15th meeting of the State Steering Committee for important national projects and works, key to the transport sector.
According to the report of the Ministry of Transport, in the past time, ministries, branches and localities have made efforts to carry out assigned tasks and works. Up to now, 41 tasks have been completed on time, 33 tasks are being carried out as regular direction and management work and 2 tasks have not yet been due.
Many difficulties and obstacles have been resolved, accelerating the progress of project implementation, including: putting the Nhon - Hanoi Railway Station elevated section into commercial operation; starting the Hoa Binh - Moc Chau project; completing the appraisal of the Ninh Binh - Hai Phong project; appraising, submitting and having the National Assembly approve the high-speed railway policy on the North - South axis, adjusting the investment policy of the Long Thanh International Airport project; issuing a Government Resolution to implement the Gia Nghia - Chon Thanh project...
Some localities have also been very determined in site clearance work and the volume has changed such as Kien Giang, Lang Son, Dong Nai.
However, 07 tasks have not been completed on time, including: Tien Giang, Ben Tre, Vinh Long, Dong Nai provinces have not completed the tasks of mine licensing procedures, increasing mine capacity for projects in the Southern region; Lam Dong Provincial People's Committee has not completed the approval of Tan Phu - Bao Loc and Bao Loc - Lien Khuong projects; Ho Chi Minh City People's Committee has not completed the task of exploiting the Ben Thanh - Suoi Tien urban railway...
Prime Minister Pham Minh Chinh.
Speaking at the meeting, Prime Minister Pham Minh Chinh commended ministries, branches, localities and units for their determination to remove difficulties and obstacles, focus on site clearance, meet material needs, mobilize forces, means and human resources, resolutely carry out construction, speed up project implementation progress...; at the same time, severely criticized units and localities for delays in project implementation.
Informing that 2025 has a special significance, with major anniversaries of the country: 95 years of the Party's founding, 50 years of the liberation of the South, national reunification, 135 years of President Ho Chi Minh's birthday, 80 years of the founding of the country; is the year of holding Party Congresses at all levels, towards the 14th National Party Congress; is also the year of reaching the finish line that determines the success of the entire 2021 - 2025 period, realizing the goal of having 3,000 km of expressways nationwide and completing the elimination of temporary and dilapidated houses nationwide, the Prime Minister requested ministries, branches and localities to overcome difficulties, make efforts to implement projects on schedule, to soon put projects into use, promote investment efficiency, contribute to the development of the country so that the people can enjoy the results.
Delegates attending the meeting.
" I request that provinces, cities, ministries, branches and relevant entities, through their specific actions, complete the 3,000 km expressway stretching from Cao Bang Lang Son to Hanoi, Da Nang to Ho Chi Minh City, Can Tho and Ca Mau. This is a project to welcome the 14th National Party Congress, demonstrating our sense of responsibility towards the country and the nation.
What we see we cannot do, we do voluntarily, what we have tried, we try harder, what we are determined, we are more determined, what we act decisively, we are more decisive.
Along with completing on schedule, quality must ensure environmental safety and technical aesthetics; One thing to note is not to use bidding as a safe haven for the blue and red armies, because checking and inspecting bidding and auctions is very grand, takes a lot of time but in the end there are still violations, still have to be handled and still take a long time, still increase the cost " - said the Prime Minister.
Along with that, the Prime Minister pointed out that promoting projects is contributing to promoting public investment disbursement, completing the task of prioritizing growth; implementing the plan to sell the right to exploit expressways to recover capital for other projects; investors, contractors, localities, units and related entities make plans to make up for lost progress...
In that spirit, the Prime Minister directed localities to mobilize the entire political system to participate, coordinate with socio-political organizations such as the Youth Union, Veterans Association, Women's Association, etc. in the localities to speed up the progress of site clearance, increase mobilization, sharing, and assistance to people to complete the handover of project sites on schedule; ensure that people can "settle down and make a living", especially during the upcoming Lunar New Year.
In addition, we must pay attention to the lives of workers and laborers on the construction site; develop a plan to prepare for Tet, especially for workers and laborers who stay on construction during Tet. Special treatment is needed so that workers can celebrate Tet, although temporarily away from their relatives and homeland, but close to joy and happiness, contributing to the development and prosperity of the country, to the era of national growth, in the spirit of "not letting brothers, sisters, and workers be lonely on the construction site".
The head of the Government requested the competent authority to urge contractors to increase machinery, equipment, and construction personnel with the spirit of "overcoming the sun, overcoming the rain, not losing to storms", "working in 3 shifts, 4 shifts", "through holidays, Tet, and days off", "eating quickly, sleeping urgently"; contributing to speeding up the construction progress, bringing the projects to the finish line ahead of schedule.
Emphasizing the review of regulations to promptly overcome shortcomings in legal and investment procedures, the Prime Minister noted that we must be determined to complete the set goals, and that we cannot adjust the goals; we must identify this as an important and top political task in the coming time to focus on direction and administration.
For some key and specific tasks, the Prime Minister assigned the Ministry of Planning and Investment to urge and accelerate the appraisal of documents, including the Tan Phu - Bao Loc, Hoa Lac - Hoa Binh projects and the renovation and upgrading of National Highway 6 through Xuan Mai - Hoa Binh. The People's Committees of Thai Binh, Ninh Binh and Lam Dong provinces proactively and actively coordinate with relevant agencies, determined to complete procedures according to regulations, ensuring the commencement of projects.
Regarding site clearance, the Prime Minister directed localities, especially Tuyen Quang, Khanh Hoa, Binh Duong, Dong Nai, Kien Giang, Bac Lieu provinces and Da Nang City to make more drastic efforts in organizing site clearance work; strictly implement Official Dispatch No. 80/CD-TTg dated August 16, 2024, ensuring the completion of handover of all remaining sites in December 2024, as a basis for completing the project in 2025.
In particular, regarding construction materials in the Mekong Delta region, the Prime Minister assigned the People's Committees of Tien Giang and Ben Tre provinces to immediately resolve procedures for granting mining licenses by volume for projects; at the same time, requested Tra Vinh province to uphold its sense of responsibility in providing river and sea sand resources for projects in the region under the direction of Deputy Prime Minister Tran Hong Ha.
The Prime Minister pointed out that the Ministry of Construction, the Ministry of Natural Resources and Environment, the Ministry of Transport, and the Ministry of Science and Technology urgently implemented the direction of Deputy Prime Minister Tran Hong Ha in Notice No. 538/TB-VPCP dated December 1, 2024 on reviewing the standards, norms, and processes for handling sea sand for construction and landfill activities, as a basis for localities to research and pilot implementation for works and projects in the area.
Emphasizing the task of implementing projects in the plan to complete 3,000 km of expressways by 2025, the Prime Minister pointed out that the goal of completing 3,000 km of expressways by 2025 is a particularly important political task of the entire Party, people, and army, especially the competent authorities assigned to implement the projects, to celebrate the 14th National Party Congress.
Therefore, Prime Minister Pham Minh Chinh requested ministries, branches, localities, and competent agencies to direct investors and contractors to coordinate with localities to remove difficulties and obstacles in site clearance, relocation of technical infrastructure, and supply of construction materials; focus, be highly determined, make great efforts, and resolutely carry out construction to speed up the progress of projects, in the spirit of "all for the people, for the development of the country".
In particular, seriously review and urgently implement key tasks to complete the goals of the emulation movement "500 days and nights of emulation to complete 3,000 km of expressway" launched by Prime Minister Pham Minh Chinh on August 18 in Dak Lak province and directed in Official Dispatch No. 673/TTg-CN dated September 5, 2024.
The Prime Minister requested that Project Management Boards need to learn from practical experience, urgently reorganize construction at the construction site, perform construction smoothly and simultaneously at many locations according to the "rolling" principle; rebuild and complete the progress critical path; urge and mobilize the total force of the main contractor and subcontractors, deploy 24/7 work using modern machinery and equipment; mobilize youth, army, police... to do public service work for manual work; urgently take stronger and more drastic action but must ensure labor safety at the construction site.
Assigning specific tasks related to the Long Thanh International Airport Construction Investment Project and Connecting Infrastructure; Terminal T3 Project, Tan Son Nhat Airport and a number of other projects in the spirit of clear people, clear work, clear agencies, units, clear products, clear completion deadlines, Prime Minister Pham Minh Chinh basically agreed with the proposals of relevant ministries, branches and localities regarding capital, policies, scale of a number of projects, innovation of the Appraisal Council's activities...; trusting the ministries, branches, localities, units, forces, related subjects and the people to join hands to promote the implementation of the projects, contributing to the realization of the double-digit economic growth target in the coming time, implementing the direction of General Secretary To Lam to bring the country into a new era - the era of national development, building a rich and prosperous country.