Vietnam.vn - Nền tảng quảng bá Việt Nam

Deputy Minister Nguyen Danh Huy inspects Hanoi railway line

Báo Giao thôngBáo Giao thông29/02/2024


With the goal of running the first freight train at Cao Xa station on April 30, 2024, the railway is speeding up construction progress to complete the temporary upgrade of Cao Xa station by April 15 with a cargo yard of about 5,400m2 for loading and unloading containers, roads to the cargo yard and station architecture to serve customers.

Next, after the Ministry of Transport approves the investment policy, phase 1 will continue to expand the cargo yard to about 10,000m2, invest in building new related construction items to be able to carry out customs procedures at the station for import and export goods.

Phase 2 will expand the station to approximately 5 hectares. The route for each phase will be based on actual freight transport needs.



Source

Comment (0)

No data
No data

Same tag

Same category

What do you need to prepare when traveling to Sapa in the summer?
The wild beauty and mysterious story of Vi Rong cape in Binh Dinh
When community tourism becomes a new rhythm of life on Tam Giang lagoon
Ninh Binh tourist attractions not to be missed

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product