Latest information on progress of items at Long Thanh airport

Báo Tuổi TrẻBáo Tuổi Trẻ10/01/2025

On the evening of January 9, Deputy Prime Minister Tran Hong Ha chaired a working session with ministries, investors and relevant units on the progress of the Long Thanh airport project.


Thông tin mới nhất về tiến độ các hạng mục ở sân bay Long Thành - Ảnh 1.

Deputy Prime Minister Tran Hong Ha noted that quality, safety and overall efficiency should come first during a working session with ministries and units on the progress of Long Thanh airport - Photo: A LOC

Reporting at the meeting, Minister of Transport Nguyen Hong Minh said that after the Prime Minister's direction, the ministry, together with the Vietnam Airports Corporation (ACV), and contractors reviewed and developed a new plan for the Long Thanh airport project.

Most items are on schedule

Accordingly, component project 1 (headquarters of state agencies) has now started construction on 4/5 projects and is committed to completing before December 31, 2025. The animal and plant quarantine station is being implemented more slowly.

For component project 2 (flight management works), it is planned to be completed before the deadline of December 31. In which, the air traffic control tower has completed the cement concrete part, and is trying to have the roof done before Tet.

Component 3 plays the most important role. The project consists of 16 construction and equipment packages. By the end of 2024, 3 basic packages will be completed, 7 packages are under construction, 3 packages are selecting construction contractors, and 3 other packages are undergoing technical design appraisal.

ACV has worked with contractors to request to speed up construction, and all parties are also making efforts to complete the packages 3-5 months ahead of schedule. However, there are still some difficulties.

In particular, package 5.10 (passenger terminal construction) is considered the "heart" of the entire project. The terminal has many complex, highly technical items, designed with advanced, modern automation technology, so shortening the progress is a big challenge.

Phó thủ tướng Trần Hồng Hà: Lấy chất lượng, an toàn và hiệu quả tổng thể lên trước hết - Ảnh 2.

Minister of Transport reports at the working session - Photo: A LOC

Calculating overall economic efficiency

After listening to reports from ministries, investors and contractors, the Deputy Prime Minister assessed that the project component 1 currently only has a quarantine station left, the Ministry of Agriculture and Rural Development has officially taken responsibility, assigned the agency and investor to carry out the procedures to complete according to schedule. However, there needs to be a monitoring mechanism, commitment to responsibility, including political, financial and economic aspects.

For component project 2, up to now, the construction part is basically 4-5 months ahead of schedule, after equipment installation, progress is at least as early as committed to the Prime Minister.

Especially for component project 3, the Deputy Prime Minister said that compared to the report to the Prime Minister, a more specific report is needed. This includes construction contents such as runways, taxiways, and parking lots.

"In general, the project component 3 is being implemented according to the committed schedule. Some items will be implemented ahead of schedule, such as the runway and taxiway. Meanwhile, the heart of the airport (package 5.10) is being implemented according to schedule, but accelerating the progress by 3-6 months compared to the contract is extremely difficult," the Deputy Prime Minister commented.

The reasons given are international contracts; complex projects implemented according to technological processes; issues related to synchronous equipment that must be signed for production and manufacturing in many places to suit us; the trial operation process... these times cannot be reduced. The issues that can be reduced require human resources, equipment and resources.

Phó thủ tướng Trần Hồng Hà: Lấy chất lượng, an toàn và hiệu quả tổng thể trên hết - Ảnh 3.

Deputy Prime Minister Tran Hong Ha and his delegation visited and worked at the office of the Vietur joint venture contractor - Photo: A LOC

The Deputy Prime Minister noted that it is necessary to clarify that reducing time and speeding up the progress of the 5.10 package requires looking at the overall progress of the items of all 4 component projects. And if there is synchronization during operation, then it will be effective in practice.

"I suggest that ACV needs to analyze very carefully during the negotiation process and report to the Prime Minister in calculating the overall economic efficiency. Putting quality, safety and overall efficiency first," the Deputy Prime Minister emphasized.

In addition, during the implementation process, the Deputy Prime Minister noted that the 5.10 package still depends heavily on the overall regulation, progress as well as the construction plan of other items that can cause overlap, contradiction, and conflict. It is also necessary to pay attention to the time to adjust the plan to ensure certainty and avoid risks.

Regarding component project 4, the Deputy Prime Minister stated that the difficulties were "behind us" and we had to look ahead. He asked the Minister of Transport to review the priority items that needed to be implemented soon to maintain the high ranking of Long Thanh airport.



Source: https://tuoitre.vn/thong-tin-moi-nhat-ve-tien-do-cac-hang-muc-o-san-bay-long-thanh-20250109202440011.htm

Comment (0)

No data
No data

Same tag

Same category

Colorful Vietnamese landscapes through the lens of photographer Khanh Phan
Vietnam calls for peaceful resolution of conflict in Ukraine
Developing community tourism in Ha Giang: When endogenous culture acts as an economic "lever"
French father brings daughter back to Vietnam to find mother: Unbelievable DNA results after 1 day

Same author

Image

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product