On June 23, Prime Minister Pham Minh Chinh led a working delegation to the construction site of the 500 kV line circuit 3 from Quang Trach (Quang Binh) to Pho Noi (Hung Yen) to inspect the construction progress and encourage the forces working on this project.
The Prime Minister and the working delegation inspected the foundation of VT22 column, located in Quynh Trang commune (Hoang Mai town, Nghe An).
The Prime Minister encouraged engineers and workers constructing the 500 kV line 3.
At the construction site, the Prime Minister commended the cadres, engineers and workers of the electricity sector for supporting the project implementation with high determination, drastic actions, arranging capital sources, focusing resources on the project, and determined to contribute to the completion of the project by June 30.
After the inspection, the Prime Minister held a meeting with relevant ministries, branches, localities and units to listen to reports and remove remaining difficulties of the project.
According to the report of Vietnam Electricity Group, up to now, on the entire route from Quang Trach (Quang Binh) to Pho Noi (Hung Yen), the foundation casting for all 1,177/1,177 pole positions has been completed; the erection of 698/1,177 pole positions has been completed, 400/1,177 pole positions are being erected; the wire pulling of 87/513 anchor intervals has been completed, and the wire pulling of 45/513 anchor intervals is being carried out.
Mr. Dang Hoang An, Chairman of Vietnam Electricity Group, affirmed that from now until the end of June, the project will be basically completed and in July, the acceptance procedures and inauguration of the entire project will be completed.
Reporting to the Prime Minister, Chairman of Nghe An Provincial People's Committee Nguyen Duc Trung said that up to now, the project through Nghe An province has been completed at 202 foundation positions, 203 column spaces, and 88 anchor spaces of the project to hand over to the investor for implementation.
The Prime Minister visited and listened to the Nghe An Provincial Youth Union report on the coordination of support for units constructing the 500 kV line.
Nghe An has 53 households affected by land acquisition for projects, of which 18 households requested resettlement land (9 households have houses on the land). The province has completed mobilizing people and households have basically agreed on resettlement locations. In case of pulling the cord and people have not resettled, the government will rent houses for households to live in to ensure safety.
In addition, Nghe An Provincial Youth Union has established 74 youth volunteer teams with the participation of more than 1,100 youth union members to support site clearance and assigned tasks.
Nghe An Youth Volunteer Force clears land for construction of 500 kV line 3
The Prime Minister acknowledged and highly appreciated the efforts of the leaders of Vietnam Electricity Group, National Power Transmission Corporation... who closely followed the construction, closely followed the project, directed and operated resolutely with the spirit of clearly defining people, clearly defining work, clearly defining progress; commended the sense of responsibility of units and localities; made efforts to "overcome the sun and overcome the rain", closely followed the progress and technical requirements of the team of engineers and workers, contributing to the success of the project.
To complete the project, there is still much work to be done. Prime Minister Pham Minh Chinh requested units and localities to launch a rapid, peak, and sprint emulation campaign to strive to complete tasks such as erecting poles, pulling wires, and conducting technical tests as required by the end of June. In July, procedures for inspection, operation, technical testing, acceptance, environmental restoration, and project inauguration will be carried out.
The 500 kV line 3 has a total length of about 519 km with a total investment of about VND 22,356 billion, including 4 component projects: Quang Trach - Quynh Luu; Quynh Luu - Thanh Hoa; Thanh Hoa - Nam Dinh 1 Thermal Power Plant and Nam Dinh 1 - Pho Noi Thermal Power Plant. The component projects were started in October 2023 and January 2024. The Prime Minister has directed to strive to complete the project before June 30, 2024.