Dong Nai will have 5 more locations for land exploitation in Bien Hoa City, Long Thanh, and Cam My to serve the land filling for Bien Hoa - Vung Tau Expressway and Ring Road 3, expected to be licensed before March 20.
According to information from the Department of Agriculture and Environment of Dong Nai, according to calculations, the Bien Hoa - Vung Tau expressway project (components 1 and 2) through Dong Nai and the Ho Chi Minh City Ring Road 3 through Dong Nai province need more than 5.24 million m3 of fill soil.
Up to now, the locality has identified locations and is able to supply 5.17 million m3, leaving a shortage of about 69,000 m3.
Currently, the demand for land to build the Bien Hoa - Vung Tau expressway is very large and urgent.
Accordingly, there are 2 locations that Dong Nai Provincial People's Committee has granted mining licenses including the mine in Phuoc Binh commune, Long Thanh district, nearly 990,000m3 and the second location in Tam Phuoc ward, Bien Hoa city, more than 210,000m3.
There are currently 5 more locations the province is considering, expected to grant licenses before March 20 for these projects.
Including mining locations in Long Giao town, Cam My district about 136,000m3; in Bau Can commune, Long Thanh district nearly 1.22 million m3; in Phuoc Tan ward, Bien Hoa about 617,000m3; in Phuoc Binh commune, Long Thanh district about 890,000m3 and in Phuoc Tan ward, Bien Hoa city about 110,000m3
In addition, there are about 1 million m3 left after completing land lease procedures for quarries in the Tam Phuoc - Phuoc Tan quarry cluster, investors will be able to reclaim the accompanying land.
Bien Hoa - Vung Tau Expressway Phase 1 has a total project length of about 53.7km. Of which, the section through Dong Nai province is about 34.2km; Ba Ria - Vung Tau province is about 19.5km. The scale of phase 1 is from 4-6 lanes, the completed expansion phase ensures the scale of 6-8 lanes. The total preliminary investment is 17,837 billion VND.
Currently, the progress of component 1 and component 2 projects through Dong Nai is only over 20-30% of output and still facing difficulties in terms of land and embankment. The section through Ba Ria - Vung Tau alone is over 74% favorable in terms of land and materials.
Source: https://www.baogiaothong.vn/them-5-vi-tri-cung-ung-5-trieu-m3-dat-dap-cao-toc-va-vah-dai-3-qua-dong-nai-19225031720170284.htm