Thang Binh removes difficulties for land exploitation projects

Việt NamViệt Nam20/12/2024


z6137571235797_f6c798645a01bd0917606365f79f2695.jpg
The new urban area project in the center of Ha Lam town (phase 1) has reached 70.5% of the volume. Photo: BIEN THUC

Mr. Truong Cong Son - Vice Chairman of Thang Binh District People's Committee said that in 2024, the District People's Committee has worked many times with investors and relevant agencies to resolve difficulties and speed up the implementation of land fund exploitation projects. However, up to now, only 4 land fund exploitation projects have basically completed construction out of a total of 15 projects eligible for implementation according to the list of approved public investment for the period 2021-2025 approved by the District People's Council.

In addition to the above 4 projects, there is 1 project that has reached 70.5% of the volume, 5 projects from 50 - 65% of the volume; there are 2 projects that have reached 10 - 35% of the volume; 1 project has not selected a contractor for the second time and 2 projects cannot be implemented. All projects under construction have extended their contracts until December 31, 2024.

bee
Mr. Le Van Thoi - Party Secretary, Chairman of Binh Que Commune People's Committee said that there was a situation where the main contractor was in the middle of construction but then dropped the bid, leading to the subcontractors also following suit. Photo: BIEN THUC

Mr. Le Van Thoi - Party Secretary, Chairman of Binh Que Commune People's Committee said that in some projects, the main contractor dropped the bid while the construction was underway, leading to subcontractors following suit. Meanwhile, the money had already been transferred to the main contractor's account, leading to sluggish projects. There needs to be a solution to tighten this.

“Because of the pressure of needing capital to invest in projects, Thang Binh district is implementing them in a scattered manner, but most of the projects are behind schedule. There is a plan to implement them in stages, so that we can achieve our expectations,” Mr. Thoi added.

Chairman of Thang Binh District People's Committee Vo Van Hung emphasized that there are 4 main reasons for the delay in land exploitation projects in the past, including the weak capacity of investors. In the coming time, Thang Binh District must make efforts in site clearance and work with project monitoring officers to speed up the implementation schedule.

draw
Affected households in the overpass area of ​​Binh Quy commune have been given resettlement land in the residential area of ​​group 3,4, Quy Thanh 1 village, Binh Quy commune. Photo: BIEN THUC

At the 20th session of the 12th District People's Council, term 2021-2026, which was just held, Mr. Phan Cong Vy - Secretary of the Thang Binh District Party Committee directed that it must be implemented resolutely, with a specific commitment to completion time, not expected to be in this quarter or that quarter.

To realize the goal of exploiting land fund of 143 billion VND next year, Thang Binh district has proposed many solutions and implementation plans for slow-progressing projects.

Accordingly, for the 4 completed projects, inspections must be conducted. If the project lacks items, additional requirements must be requested to ensure compliance with regulations. Procedures for land recovery and land allocation to the District Land Fund Development and Industry - Service Center must be established to organize auctions. For the 9 projects that have not been completed, priority groups must be assigned to complete them according to specific timeframes, construction must be accelerated, and acceptance must be completed and put into use in 2025.

z6137632637129_71af14cb0d6242d6d0727b7fad270ebb.jpg
Residential area of ​​group 3,4, Quy Thanh 1 village (Binh Quy) is now eligible for construction. Photo: BIEN THUC

Of which, for 8 land exploitation projects stuck with site clearance, Thang Binh district requested the investor to urge the contractor to complete the items and work on the handed-over site, not to delay the situation of using the excuse of not handing over the site. Thang Binh district will also consider penalizing the contract for the work on the handed-over site but not affected by the work not yet cleared.

“We must attach responsibility to specialized agencies and localities for implementation. In early 2025, Thang Binh district will organize a thematic conference to discuss solutions for implementing land exploitation projects in the locality. In addition, Thang Binh district will also consider the responsibility of related units that intentionally delay and delay the progress of projects,” said Mr. Phan Cong Vy, Secretary of Thang Binh District Party Committee.



Source: https://baoquangnam.vn/thang-binh-thao-go-kho-khan-cac-du-an-khai-thac-quy-dat-3146321.html

Comment (0)

No data
No data

Same tag

Same category

Luc Yen, a hidden green gem
Spreading national cultural values ​​through musical works
Lotus color of Hue
Hoa Minzy reveals messages with Xuan Hinh, tells behind-the-scenes story of 'Bac Bling' causing global fever

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product