Focus on directing and striving to complete disbursement of 95% of the assigned plan.

Việt NamViệt Nam27/12/2024


BPO - The People's Committee of Binh Phuoc province has just issued Official Dispatch No. 5453/UBND-TH on promoting the disbursement of public investment capital in the remaining period of 2024.

Accordingly, the Chairman of the Provincial People's Committee directed: For projects that have completed or are under construction, the People's Committees of districts, towns, cities and investors must urgently complete the documents, legal procedures, and acceptance documents of completed volumes and send them to the State Treasury before December 31, 2024.   as a basis for control, payment and refund according to regulations (time for disbursement of public investment capital in 2024 to January 31, 2025).

The Department of Natural Resources and Environment shall preside over and coordinate with relevant units and localities to advise the Provincial People's Committee to urgently continue to remove difficulties and obstacles in the auction of land use rights with the highest results to have a source of revenue for disbursing public investment capital.

The People's Committees of districts, towns, cities and investors urgently review the detailed disbursement plans of each project, especially projects in the group with a disbursement rate of less than 50%. At the same time, for decentralized capital of districts, towns, and cities in the group with low disbursement rates (less than 70%), localities are required to focus on directing to strive to complete the disbursement at 95% of the assigned plan.

The Chairman of the Provincial People's Committee requested the Chairmen of the People's Committees of districts, towns, and cities and the heads of agencies and units assigned as investors to review the responsibilities of agencies, units, and localities that did not complete the disbursement task in 2024 before the Provincial People's Committee and the Chairman of the Provincial People's Committee.

Regarding decentralized capital for districts, towns and cities, the Chairman of the Provincial People's Committee requested the Chairmen of the People's Committees of districts, towns and cities to resolutely direct the detailed allocation of capital plans to ensure focus, key points, not spread out, in accordance with the implementation capacity and disbursement in accordance with the legal provisions on public investment. At the same time, accelerate the disbursement of capital that has been approved by the Provincial People's Council to extend the implementation period and disbursement of local budget sources in 2023 to 2024. The People's Committees of districts, towns and cities are responsible to the inspection and auditing agencies, the Provincial People's Committee and the Chairman of the Provincial People's Committee for the allocation and disbursement of assigned decentralized capital.



Source: https://baobinhphuoc.com.vn/news/53/167141/central-committee-initial-department-completed-95-delivery-plan

Comment (0)

No data
No data

Same tag

Same category

What do you need to prepare when traveling to Sapa in the summer?
The wild beauty and mysterious story of Vi Rong cape in Binh Dinh
When community tourism becomes a new rhythm of life on Tam Giang lagoon
Ninh Binh tourist attractions not to be missed

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product