Increase machinery, change plan to overcome landslide in Chi Thanh railway tunnel

Báo Giao thôngBáo Giao thông21/05/2024


According to Giao thong Newspaper reporters at the scene, dozens of workers, engineers and specialized machinery and equipment are being transported into the tunnel area by Project Management Board 85 (the investor of the Chi Thanh railway tunnel reinforcement project and other railway tunnels) along with Phu Khanh Railway Exploitation Branch and functional units to reinforce and repair landslides.

Tăng máy móc, thay đổi phương án khắc phục sạt lở hầm đường sắt Chí Thạnh- Ảnh 1.

Authorities brought machinery inside to fix the landslide.

According to Mr. Le Quang Vinh, Director of Phu Khanh Railway Exploitation Branch, the initial cause of the landslide was determined to be due to rain in the area in recent days, leading to weak geological layers causing landslides.

Tăng máy móc, thay đổi phương án khắc phục sạt lở hầm đường sắt Chí Thạnh- Ảnh 2.

Landslide remediation work is being urgently carried out.

The exact time when the problem will be fixed is still unknown. Workers are focusing on solutions. Currently, the volume of soil and rock that has collapsed inside the tunnel is about 50m3, completely blocking the area of ​​the iron tunnel.

Learning from the experience of the landslide at Bai Gio tunnel (Khanh Hoa province), the workers of Phu Khanh Railway Exploitation Branch did not remove the landslide but instead sealed it to create a support base above the tunnel roof.

Accordingly, workers will drill to create anchors and spray concrete on the tunnel lining to create a solid connection, then clear the soil and rocks below.

Currently, cargo ships are bringing in machinery to prepare for drilling anchors at both the South and North ends of the tunnel.

Tăng máy móc, thay đổi phương án khắc phục sạt lở hầm đường sắt Chí Thạnh- Ảnh 3.

The landslide site has been reached.

Tăng máy móc, thay đổi phương án khắc phục sạt lở hầm đường sắt Chí Thạnh- Ảnh 4.

Work to repair the landslide in the Chi Thanh railway tunnel is being carried out urgently.

The railway sector has also developed a plan to transfer passengers from Tuy Hoa station and La Hai station, ensuring the travel schedule of passengers. The Phu Yen Province Traffic Inspectorate is also present on Provincial Road 641, above the Chi Thanh Railway Tunnel area, to regulate traffic.

Previously, at around 10:30 a.m. on May 21, the Chi Thanh railway tunnel, while being closed for renovation, suddenly experienced a landslide on the tunnel ceiling, sealing the tunnel.

No trains are running at this time. Authorities are urgently fixing the problem. The Chi Thanh railway tunnel area is currently being invested in by Project Management Board 85 (Ministry of Transport) to carry out repairs and upgrades.



Source: https://www.baogiaothong.vn/tang-may-moc-thay-doi-phuong-an-khac-phuc-sat-lo-ham-duong-sat-chi-thanh-192240521180904768.htm

Comment (0)

No data
No data

Same tag

Same category

Vietnam calls for peaceful resolution of conflict in Ukraine
Developing community tourism in Ha Giang: When endogenous culture acts as an economic "lever"
French father brings daughter back to Vietnam to find mother: Unbelievable DNA results after 1 day
Can Tho in my eyes

Same author

Image

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product