By the end of September, Son La province's public investment capital disbursement had reached VND1,919 billion, equivalent to 43.64% of the assigned capital plan. Implementing "5 determinations" and "5 guarantees" in implementation, Son La strives to achieve the goal of completing the disbursement of assigned capital in 2024.
Many units have high disbursement rates
In 2024, the total public investment capital of Son La province is nearly 4,398 billion VND, of which the previous year's capital plan is allowed to extend the implementation period to 2024 by over 509 billion VND; the capital plan for 2024 is over 3,888 billion VND. Due to complicated weather conditions, floods and rains have affected the construction progress of works and projects. However, with the determination and efforts of the province, departments, branches, localities, and investors, many works and projects have accelerated site clearance to start new construction, and many construction works are ahead of schedule.
Comrade Nguyen Minh Tien, Director of the Department of Planning and Investment, said: The Department has worked with 12 districts and cities to review and evaluate the implementation of the 2024 public investment plan; disbursement results are updated weekly on the Intelligent Operation Center (IOC) to serve the province's operational activities. At the same time, monthly disbursement results for each investor are made public at the regular meeting of the Provincial People's Committee and posted on the province's electronic information portal. Thereby, promptly assessing the progress of each investor's plan implementation, directing solutions to remove and overcome difficulties for investors and projects behind schedule. The overall disbursement results of the whole province as of September 20 reached 43.64% of the total assigned capital plan, equal to 48.76% of the detailed allocated capital, higher than the same period in 2023.
Leading the localities in terms of public investment disbursement rate is Son La city. By September 27, the city had disbursed over 215 billion VND, reaching 80.7% of the assigned capital plan, higher than the average disbursement rate of the whole province. From this capital source, many works and projects have been completed and handed over for use ahead of schedule. Typical: Chieng Den Kindergarten; renovation and repair project of Chieng Le Primary School; Lo Van Gia Primary School; investment and upgrading of Le Quy Don Secondary School; Cultural House and auxiliary items of Hua La commune; upgrading and renovating the sidewalk of 3/2 street; resettlement area No. 2, Me Ban village, Chieng Coi ward...
In Muong La district, in 2024, 134 projects will be implemented, with a total investment of over 680 billion VND. To date, over 206 billion VND has been disbursed, reaching 65% of the assigned capital plan. Comrade Nguyen Van Tam, Vice Chairman of the District People's Committee, informed: The District People's Committee has established a working group to inspect, urge, direct, proactively remove difficulties and obstacles, speed up compensation progress, site clearance, construction progress of key works and projects, as a basis for accelerating disbursement of public investment capital. Weekly meetings are held, investors report on disbursement progress every 15 days to grasp progress, difficulties and obstacles for timely removal.
Along with that, Muong La District People's Committee has strengthened inspection and supervision of the project, requiring representatives of investors to always closely follow the situation, grasp difficulties and find timely solutions; complete payment procedures immediately after the volume is accepted, not to accumulate in the last months of the year. During the implementation process, promptly commend and reward investors who do well; criticize investors who are slow to disburse capital.
Muong La District General Hospital Project (Phase II), with a total investment of 81 billion VND, started construction in July 2023, and to date the project has completed 78% of the volume. Mr. Nguyen Van Tinh, Project Manager, Viet Dung Joint Stock Company, shared: During the project implementation process, the investor was regularly present at the site to coordinate in resolving difficulties and problems during the construction process. Currently, the project is in the finalization stage, the contractor has focused on increasing equipment, human resources, and materials to the construction site, organizing construction measures in shifts, ensuring to speed up the project's construction progress. The project is expected to be completed in December 2024.
The Management Board of Investment Projects for Construction of Civil and Industrial Works and Urban Development is also a bright spot in the disbursement of public investment capital. In 2024, the investment capital plan is assigned over 59.7 billion VND to build a 9-storey office building and 2 6-storey buildings belonging to the headquarters of the People's Council, People's Committee, Vietnam Fatherland Front Committee of the province and a number of departments and branches of the province. By June 30, 100% of the assigned capital had been disbursed and paid.
Efforts to complete disbursement target
The overall disbursement progress of the whole province as of September 20 reached 43.64%, the reason for the low achievement was due to the slow implementation of the detailed allocation plan for 2024 for some capital sources. Specifically, the disbursement of National Target Programs (NTPs) in the province is still slow. These projects still face many difficulties and obstacles due to the mechanisms, policies, and contents that need to be revised, supplemented, and adjusted many times, affecting the progress of the implementation of projects and sub-projects at all levels and sectors. In particular, the mechanisms and policies related to the implementation of production development support projects are slow to be issued and completed, leading to the contents of production development support not being implemented.
With the motto "wherever there is a problem, there is a solution", in the last months of the year, the Provincial People's Committee directed departments, branches, districts and cities to resolutely and synchronously implement solutions to promote disbursement of public investment capital according to Directive No. 26/CT-TTg dated August 8, 2024 of the Prime Minister. The focus is on seriously implementing the commitment to disburse capital for each project and each capital source; strengthening discipline and order in disbursing public investment capital. Focus on accelerating the progress of site clearance, construction progress, making advances, acceptance, payment, and recovering advances in accordance with regulations and immediately after the volume is available.
In particular, the Provincial People's Committee directed the implementation of "5 resolutions" which are: Maintaining discipline, pushing back negativity in disbursing public investment capital; doing well in site clearance, resettlement, creating livelihoods for people; removing bottlenecks affecting the progress of public investment capital disbursement; innovating methods and approaches; sticking to reality, removing obstacles, overcoming the situation of pushing, avoiding, fear of mistakes, fear of responsibility in performing public duties of cadres, civil servants and public employees.
Along with that, the Provincial People's Committee directed to implement "5 guarantees", including: Sufficient materials, especially sand, stone, gravel, soil for embankment... to serve the construction of projects, especially key projects of the province and district; sufficient human resources, selecting cadres with sufficient capacity, dedication, and capacity, assigning tasks related to disbursement of public investment capital; ensuring harmony of interests between the State, investors and people in implementing and carrying out site clearance, resettlement, and creating livelihoods for people in the spirit of not leaving anyone behind, the new place of residence must be at least equal to or better than the old place of residence; managing public investment in accordance with regulations, not prolonging project implementation time, increasing the total project investment, causing capital loss, reducing investment efficiency; ensuring progress and quality according to the set goals and planning, and ensuring labor safety and environmental sanitation in project implementation.
With specific solutions in the direction of "5 clear" - clear people, clear work, clear progress, clear results, clear responsibilities in implementation, we believe that the disbursement progress of public investment capital of Son La province in 2024 will be completed as planned, contributing to promoting the local socio-economy.
Minh Thu
Source: https://baosonla.org.vn/kinh-te/son-la-thuc-hien-5-quyet-tam-va-5-dam-bao-trong-giai-ngan-von-dau-tu-cong-gQmk3VkHR.html
Comment (0)