According to the Management Board of Transport and Agriculture Projects of Bac Ninh Province (Investor of the Ring Road 4 project - Hanoi Capital Region in Bac Ninh Province), by April 18, localities had approved the compensation plan for 371/374 hectares (land area within the 90m boundary), reaching 99.3%; The remaining 2.56 hectares, accounting for 0.7%, had approved the compensation plan but households had not received the money.
As of April 18, localities have compensated 371/374 hectares, reaching a rate of 99.3%.
Specifically, Bac Ninh city still has 27 households, corresponding to an area of over 7,100 m2; Que Vo town still has 27 households; Thuan Thanh town still has 54 households whose residential land must be recovered but have not received compensation or site clearance. The total construction value up to this point has reached 32%. Of which: Package 14 reached 41%, Package 15 reached 29%, Package 16 reached 27.2%. The disbursement value on the construction output on the construction site is 368.32/740.5 billion VND.
The biggest difficulty and obstacle at present is that some residential land areas and land allocated beyond authority have not been handed over as planned; Land areas outside the 90-meter boundary to serve the construction of irrigation works, intersections, roads, and canal improvements have not been approved yet.
Based on the approved overall construction schedule and the sections with cleared land, the investor directs the contractor to mobilize maximum resources, machinery, equipment and materials to carry out the construction. For the People's Committees of Bac Ninh City , Que Vo Town and Thuan Thanh , consider and direct the Compensation and Site Clearance Council to promptly hand over the residential land area, land allocated beyond authority, disputed farm land, land outside the 90-meter boundary to serve the construction of intersections, roads and ditch improvements to the investor in April 2025; Contractors proactively seek sources of sand, soil, crushed stone aggregate and gather and mobilize them to the construction site, deploy construction to ensure progress as committed.
Phuong Hoa, Quoc Hung