Good coordination, removing difficulties to implement the North expressway project

Việt NamViệt Nam09/09/2023

Chairman of the Provincial People's Committee Vo Trong Hai requested units and localities to coordinate with investors and contractors to resolve difficulties and ensure smooth construction of the North-South expressway project through Ha Tinh.

On the morning of September 9, Chairman of the Provincial People's Committee Vo Trong Hai and a working delegation inspected the progress and handled problems related to compensation, support, resettlement, exploitation and supply of construction materials (VLXD) for the North-South Eastern Expressway project in the 2021-2025 period through Ha Tinh province.

Colonel Nguyen Hong Phong - Member of the Provincial Party Committee, Director of the Provincial Police, leaders of departments, branches, representatives of investors, construction units and localities: Ky Anh, Cam Xuyen, Thach Ha, Can Loc districts accompanied the delegation.

Good coordination, removing difficulties to implement the North-South expressway project through Ha Tinh

Chairman of the Provincial People's Committee Vo Trong Hai and the working delegation inspected the Dat Do 2 landfill in Ky Trung commune.

Chairman of the Provincial People's Committee Vo Trong Hai and the working delegation inspected the Dat Do 2 landfill in Ky Trung commune, the site clearance work of Ky Anh district; Dong Chieng landfill in Cam Son commune (Cam Xuyen), problems with site clearance in Cam Quan commune, relocation of the solar power plant infrastructure in Cam Xuyen district; problems with relocation of pig farms in Viet Tien commune and site clearance work of some landfills in Thach Ha district; the progress of construction of resettlement areas and problems with site clearance in Kim Song Truong commune, Can Loc district.

Good coordination, removing difficulties to implement the North-South expressway project through Ha Tinh

Construction of the North-South expressway project through Thach Ha district.

During the inspection, representatives of the Thang Long Project Management Board (Ministry of Transport) - the investor of the two North-South expressway component projects, Bai Vot - Ham Nghi, Ham Nghi - Vung Ang sections, and leaders of the districts: Ky Anh, Cam Xuyen, Thach Ha, Can Loc reported to the working delegation on the project's site clearance progress, construction material sources and related problems.

Thang Long Project Management Board highly appreciates the participation of departments, branches and localities in Ha Tinh in implementing site clearance work when handing over the site at a high rate, ensuring the contractor can carry out construction.

Good coordination, removing difficulties to implement the North-South expressway project through Ha Tinh

Chairman of the Provincial People's Committee Vo Trong Hai and the working delegation inspected the Dong Chieng landfill in Cam Son commune, Cam Xuyen district.

However, there are still some unresolved problems that need to be resolved soon to meet the goal of shortening the progress and creating favorable conditions for construction.

Regarding the source of construction materials, the Provincial People's Committee has approved the confirmation of 11/11 mines as proposed by the investor and construction contractor. The contractors have been implementing steps to exploit but are still facing difficulties, including the inability to agree on compensation prices with some households.

Good coordination, removing difficulties to implement the North-South expressway project through Ha Tinh

The Chairman of the Provincial People's Committee listened to a report on the progress and some difficulties in site clearance for the North-South expressway project through Thach Ha district.

During the process of on-site inspection and listening to progress reports and difficulties in compensation, support, resettlement, exploitation and supply of construction materials for project construction, Chairman of the Provincial People's Committee Vo Trong Hai acknowledged and commended the efforts of units and localities in implementing site clearance and providing construction materials, facilitating the project construction process.

The Chairman of the Provincial People's Committee emphasized: The North-South Expressway is a national key project, receiving great attention from the Government, the Prime Minister and the Ministry of Transport, so units and localities must focus highly, promptly complete the handover of the site to the investor and meet the source of construction materials for the project.

Good coordination, removing difficulties to implement the North-South expressway project through Ha Tinh

The Chairman of the Provincial People's Committee listened to a report on site clearance work for the North-South expressway project through Kim Song Truong commune, Can Loc district.

Chairman of the Provincial People's Committee Vo Trong Hai requested units and localities to actively coordinate and exchange information with investors and contractors when implementing site clearance and construction material sources, especially in resolving difficulties and obstacles. In cases beyond their authority, localities must promptly report for timely handling.

Localities need to speed up the process of building resettlement areas; implement compensation, support and resettlement work in accordance with legal regulations; continue to propagate and mobilize people to comply with regulations on site clearance and land handover for project implementation.

Good coordination, removing difficulties to implement the North-South expressway project through Ha Tinh

People build houses in the resettlement area of ​​Dong Vinh village, Kim Song Truong commune, Can Loc district.

The Department of Agriculture and Rural Development shall preside over and coordinate with investors to resolve issues related to the implementation of replacement forest planting obligations and plans for exploiting forest products when exploiting construction material mines; the Department of Natural Resources and Environment shall coordinate and support localities in resolving land-related problems in project site clearance.

In some cases where people refuse to receive compensation, even though the procedures for site clearance and compensation have been implemented in accordance with regulations and have been publicized and explained, localities need to take measures to handle them in accordance with regulations.

The police force investigates, reviews, and consolidates records to strictly handle subjects who show signs of inciting, dragging, and inciting people not to receive compensation for land acquisition and clearance. Resolutely not to let the issue of land and construction materials affect the progress of the North-South expressway through Ha Tinh.

For investors and contractors, it is necessary to focus on human resources and machinery to speed up project construction progress as the rainy and stormy season is approaching; and to proceed with exploitation of the mineral mine areas that have completed documents and procedures.

The North-South Eastern Expressway Project, phase 2021-2025, through Ha Tinh province, has a length of 102.38 km with 3 component projects: Bai Vot - Ham Nghi, Ham Nghi - Vung Ang, Vung Ang - Bung and 3 connecting routes, 12.18 km long.

Up to now, Ha Tinh has counted 100% of land acquisition and clearance; applied prices and approved compensation plans at 99.07% and handed over land at 98.03%. The progress of disbursement of land acquisition and clearance capital is 2,116.21/2,853.43 billion VND, reaching 74.16%.

26 resettlement areas and 4 cemeteries have all been constructed, of which 8 areas have reached 100% completion, the remaining areas have reached 20-97% completion; the Department of Information and Communications and telecommunications enterprises have agreed on a plan to relocate the telecommunications system.

The relocation of power line infrastructure is being actively implemented by localities in coordination with electricity agencies.

Van Duc - Le Tuan


Source

Comment (0)

No data
No data

Same tag

Same category

Same author

Figure

French father brings daughter back to Vietnam to find mother: Unbelievable DNA results after 1 day
Can Tho in my eyes
17-second video of Mang Den so beautiful that netizens suspect it was edited
The primetime beauty caused a stir because of her role as a 10th grade girl who is too pretty even though she is only 1m53 tall.

No videos available