Also attending were representatives of the leaders of the Departments: Finance, Construction, Provincial Police, Provincial People's Committee Office, and Provincial Construction Investment Project Management Board.

In Hiep Luc commune, through actual inspection, it shows that the construction progress of Hiep Luc Primary School has reached about 80% of the volume; Hiep Luc Kindergarten has reached about 60% of the volume, the construction unit is focusing on implementation, striving to complete in June 2025. Regarding the Hiep Luc Commune Police Headquarters, the implementation has reached about 90% of the volume, striving to complete construction and handover for use in early April 2025. Regarding the work of removing temporary and dilapidated houses, Hiep Luc commune has carried out a total of 91 houses, up to now, 10 houses are being renovated and 1 house is being repaired. Many households have added money to build new houses with an estimated value of 150 to 300 million VND.

In Van Tung town, the delegation inspected the progress of the Ngan Son District Medical Center Construction Investment Project, under the National Target Program for Socio-Economic Development in Ethnic Minorities and Mountainous Areas. Currently, the construction unit is focusing on building the Block House and functional departments... the total volume has reached about 30% of the plan, striving to complete by September 30, 2025. For the Van Tung Kindergarten Construction Project, the rough construction has been completed, the auxiliary items are being completed, striving to complete by July 25, 2025.

Regarding the progress of removing temporary and dilapidated houses, the whole district has implemented 559 houses, currently more than 40 houses have been started and are under construction. The Steering Committee of the district and commune is focusing resources to ensure progress in the coming time.

At the inspection sites, Vice Chairman of the Provincial People's Committee Hoang Thu Trang praised the units for their efforts and good results. He directed that in the coming time, units and localities continue to strengthen coordination to implement convenient contents. Take advantage of favorable weather to concentrate machinery and human resources to speed up the construction progress of items and works. Ensure quality and progress as committed, construction must ensure safety; investors need to strengthen inspection and supervision to detect difficulties and obstacles for timely resolution./.
Source: https://baobackan.vn/pho-chu-tich-ubnd-tinh-hoang-thu-trang-kiem-tra-tien-do-cac-du-an-xay-dung-tai-ngan-son-post69853.html