Relevant units are urgently constructing the Chau Doc - Can Tho - Soc Trang expressway project, the section passing through An Giang province, and the first meters of asphalt have been paved at this project.
At package No. 43, Mr. Nguyen Manh Tuan, Project Executive Director, Phuong Thanh Investment and Construction Joint Stock Company (construction contractor) said that up to now, the progress of the package location under the contractor's responsibility has reached 54.16% of the contract value.
The first meters of asphalt have been paved on the Chau Doc - Can Tho - Soc Trang highway.
At the construction site, the contractor arranged 10 construction teams, with a total of nearly 230 workers working continuously on the construction site. In addition, the contractor also arranged 98 equipment and 3 cement concrete mixing stations within the construction area.
Currently, the contractor has completed the entire substructure, combined with the production and installation of all 8 bridges under the contractor's responsibility. Regarding the road section, the contractor has installed 0.04/4.6km of waterproofing wicks.
In particular, the first meters of asphalt have also been paved by the contractor on the overpass, at the highway intersection with Provincial Road (DT) 945 - the road connecting Chau Phu district, An Giang province to Hon Dat district, Kien Giang province. This is the DT945 overpass, crossing the Chau Doc - Can Tho - Soc Trang highway, the section through An Giang province, which is under the contractor's responsibility for construction.
"The contractor will complete the asphalt paving of the overpass at the intersection with Route 945 before December 31. The contractor plans to open this intersection to traffic before the Lunar New Year (January 25, 2025) to facilitate people's travel during the 2025 Lunar New Year," Mr. Tuan added.
The contractor strives to open the technical traffic before Lunar New Year 2025.
The Management Board of Investment Projects for Construction of Transport and Agriculture Works of An Giang Province (investor) said that the Chau Doc - Can Tho - Soc Trang Expressway Phase 1 has a total length of 188.2km passing through four provinces and cities: An Giang, Can Tho, Hau Giang and Soc Trang.
The section through An Giang province is component 1 of the project, 57.2km long and with a total investment of VND13,526 billion. The project is divided into 4 construction packages and numbered 42, 43, 44 and 45.
The total output of the 4 main construction packages reached 39.56/39.42%, exceeding by about 0.14%. Of which, the progress of package 42 reached 31.61%; package 43 reached 39.61%; package 44 reached 53.02% and package 45 reached 35.57%.
The Chau Doc - Can Tho - Soc Trang expressway project phase 1 has a total length of 188.2km passing through 4 provinces and cities: An Giang, Can Tho, Hau Giang and Soc Trang.
The starting point connects to National Highway 91 in Chau Doc city (An Giang) and the end point intersects with Nam Song Hau National Highway, connecting to Tran De port access road (Soc Trang), with a total investment of 44,691 billion VND. The entire route is expected to be completed and put into use in 2027.
Of which, component project 1 in An Giang province is 57.2km long, component project 2 in Can Tho city is 37.2km long, component project 3 in Hau Giang province is nearly 37km long and component project 4 in Soc Trang province is 56.9km long.
In phase 1, the project will be invested in a 4-lane scale, with a design speed of 100km/h. In the final phase, the project will be invested in a 6-lane scale.
Source: https://www.baogiaothong.vn/nhung-met-nhua-dau-tien-duoc-tham-tren-cao-toc-chau-doc-can-tho-soc-trang-192241226174122276.htm