Contractor for the Chau Doc - Can Tho expressway

Báo Xây dựngBáo Xây dựng30/09/2024


Overcoming floods, accelerating construction.

At the construction site of the Western Vietnam cross-section expressway, specifically the section passing through An Giang province, reporters from Giao Thong Newspaper observed hundreds of workers and dozens of pieces of equipment and machinery working daily.

Nhà thầu thi công cao tốc Châu Đốc - Cần Thơ - Sóc Trăng chạy đua với lũ ĐBSCL- Ảnh 1.

The contractor proactively divided the project into sections and carried out construction during the flood season for the Chau Doc - Can Tho - Soc Trang expressway section passing through An Giang province.

Regarding package number 42, Lieutenant Colonel Nguyen Thanh Nhang, Deputy Director of the Truong Son 11 Project Management Board, Truong Son Construction Corporation, stated that the section of the expressway passing through An Giang province is nearly 14km long. Of that, approximately 4km is located in a flood-prone area.

To proactively respond, the contractor organized workers to carry out construction work in these areas before the floodwaters inundated the fields.

Currently, the abutments for five bridges under the contract have been completed, and girder installation is underway. The bridge decks are expected to be largely completed by mid-December. Many other components of these bridges are also targeted for completion this year.

Nhà thầu thi công cao tốc Châu Đốc - Cần Thơ - Sóc Trăng chạy đua với lũ ĐBSCL- Ảnh 2.

Contractors are accelerating construction progress on the Western Vietnam cross-region expressway.

For road sections located in flood-prone areas, the contractor is proactively carrying out construction even during the flood season, and workers are currently installing drainage wicks.

"The construction site receives 2,000 cubic meters of sand per day, concentrating it in key areas and those at risk of flooding for prioritizing construction. The purpose is to ensure that construction is not affected when floods inundate the fields."

"These locations have basically recovered from the floods, and workers are working continuously to speed up the progress," Lieutenant Colonel Nhang said.

Bring in more workers to the construction site in October.

According to Lieutenant Colonel Nhàng, the construction progress currently stands at over 25%, exceeding the plan by 0.5%. The contractor demonstrated great determination to achieve this result.

"We've organized the workers into two shifts, from 7 am to 11 pm, adding four hours to their normal working hours. We expect the contractor to add 60 more workers to the construction site in October," Mr. Nhàng said.

Nhà thầu thi công cao tốc Châu Đốc - Cần Thơ - Sóc Trăng chạy đua với lũ ĐBSCL- Ảnh 3.

Many sections of the Western Vietnam expressway, particularly the section passing through An Giang province, have been fitted with drainage wicks.

Mr. Tran Minh Khang, a technical officer at Tan Nam Construction Joint Stock Company (the contractor), said that package number 45, undertaken by the company, is 5.3km long and includes 3 bridges. To date, the construction progress has reached 26%.

On the construction site, the contractor is having workers drill bored piles, construct soil-cement piles, build abutments, cast beams, and install drainage wicks.

The company deployed 100 workers along with 22 machines and pieces of equipment. The workers were organized into 3 shifts with 6 construction teams, working from 7:00 AM to 11:00 PM each day.

Nhà thầu thi công cao tốc Châu Đốc - Cần Thơ - Sóc Trăng chạy đua với lũ ĐBSCL- Ảnh 4.

Workers are working overtime on the Chau Doc - Can Tho - Soc Trang expressway construction site, the section passing through An Giang province.

The An Giang Provincial Project Management Board for Investment in Construction of Transportation and Agriculture Projects (the investor) announced that the Chau Doc - Can Tho - Soc Trang expressway section passing through the province has four bidding packages: 42, 43, 44, and 45. The total progress has reached nearly 30%, exceeding the planned schedule.

Phase 1 of the Chau Doc - Can Tho - Soc Trang expressway project has a total length of 188.2km, passing through four provinces and cities: An Giang, Can Tho, Hau Giang, and Soc Trang.
The route starts at National Highway 91 in Chau Doc City (An Giang province) and ends at the intersection with the Southern Hau River National Highway, connecting to the Tran De Port access road (Soc Trang province), with a total investment of 44,691 billion VND. The entire route is expected to be completed and put into operation in 2027.
Specifically, component project 1 in An Giang province is 57.2km long, component project 2 in Can Tho city is 37.2km long, component project 3 in Hau Giang province is nearly 37km long, and component project 4 in Soc Trang province is 56.9km long.
Phase 1 of the project involves the construction of a 4-lane road with a design speed of 100 km/h. The completed phase will expand the project to 6 lanes.



Source: https://www.baogiaothong.vn/nha-thau-thi-cong-cao-toc-chau-doc-can-tho-soc-trang-chay-dua-voi-lu-dbscl-192240930162857113.htm