Opening the right tunnel door on the west side of tunnel number 2 of Dong Dang - Tra Linh highway
On the Dong Dang - Tra Linh expressway, 2 tunnels will be built through the mountain, of which tunnel number 2 at Km72 (Thach An district, Cao Bang province) includes 2 tunnels nearly 500m long, considered one of the critical roads of the project's progress.
![]() |
Special equipment for construction of Dong Dang - Tra Linh expressway tunnel. |
On June 21, the contractor consortium led by Deo Ca Group opened the right gate of the western tunnel No. 2 of the Dong Dang (Lang Son) - Tra Linh (Cao Bang) Expressway Project, Phase 1. This is the first tunnel gate to be opened on the entire route of this expressway project.
Tunnel No. 2 was built at about Km72 (Thach An district, Cao Bang province) including 2 tunnel tubes (left, right) nearly 500m long.
According to the report of Dong Dang - Tra Linh Expressway Joint Stock Company - Project Enterprise, as of mid-June 2024, Cao Bang Provincial People's Committee has handed over the site for the construction site through Cao Bang province under the PPP project to invest in Dong Dang - Tra Linh Expressway, reaching 35.36/41.55 km, equivalent to 85%, meeting the construction schedule.
It is expected that by July 2024, the People's Committee of Cao Bang province will complete 100% of site clearance work in this locality.
For the scope in Lang Son province, the volume of land handed over to the new construction unit has reached 5.45/51.8 km, equivalent to 10.5%. According to the plan, Lang Son People's Committee will complete the site clearance work for the Dong Dang - Tra Linh expressway within Lang Son province in September 2024.
A representative of Dong Dang - Tra Linh Expressway Joint Stock Company said that despite receiving attention and direction from the Prime Minister and leaders of the two provinces, the volume of earth filling materials for the entire project is currently lacking about 4 million m3. In addition to adding 4 new earth quarries, the project enterprise has carried out construction of leveling and leveling the areas around the project. Currently, the project enterprise is coordinating with relevant parties to carry out procedures with the provincial authorities to complete the licensing of exploitation to exploit the earth quarries according to the special mechanism.
To speed up the construction progress, the Project's construction units mobilized 467 personnel, 199 machines and equipment, deployed 19 construction teams to simultaneously approach and organize construction according to the handed-over site segments.
“We are researching to launch a competition movement and build a reward mechanism for contractors to promote construction activities of the entire project,” said a representative of Dong Dang – Tra Linh Expressway Joint Stock Company.
According to Mr. Nguyen Duc Tuan - Deputy General Director of Dong Dang - Tra Linh Expressway Joint Stock Company, although the construction of tunnel No. 2 has been opened, the site for the waste dump and the functional area of the concrete mortar mixing station has not been handed over. He proposed that the People's Committee of Cao Bang province speed up site clearance and agree to supplement the waste dumps arising during the construction process.
Mr. Nguyen Duc Tuan hopes that Cao Bang Provincial People's Committee will continue to work with Lang Son Provincial People's Committee and the Government to supplement enough land use quotas for the project in the fourth quarter of 2024; approve the addition of 4 soil material mines as proposed by Dong Dang - Tra Linh Expressway Joint Stock Company; at the same time, approve the plan to renovate and utilize surplus land in accordance with regulations to meet the source of construction soil materials.
Previously, on June 11, 2024, the Steering Committee of the Dong Dang - Tra Linh Expressway Project held a meeting to evaluate the project implementation results and continue to promote the implementation of key tasks.
Mr. Tran Hong Minh, Secretary of Cao Bang Provincial Party Committee, requested the People's Committees of districts where the project passes through to urgently approve plans and estimates for compensation for land acquisition and clearance for local people, and strive to hand over 100% of the site to Dong Dang - Tra Linh Expressway Joint Stock Company for construction on schedule.
“The People’s Committees of the districts, within their authority, need to quickly implement procedures for exploiting minerals for common construction materials for the project after the Government issues Resolution No. 106/2003/QH15. Actively work with Lang Son province to adjust the route, clear the land, and change the purpose of forest use for the project,” Secretary Tran Hong Minh directed.
The Dong Dang – Tra Linh Expressway Project has a total length of 121km, divided into 2 investment phases. In phase 1, the Dong Dang – Tra Linh Expressway is invested with a length of more than 93km. The starting point is at the Tan Thanh border gate intersection (Van Lang district, Lang Son province). The end point is at the National Highway 3 intersection (Chi Thao commune, Quang Hoa district, Cao Bang province). Deo Ca Group is the leading investor of the consortium implementing the Phase 1 Project.
The completion of the Dong Dang – Tra Linh Expressway will play a role in strengthening domestic and international trade connections, contributing to improving the competitiveness of localities and regions, creating momentum for socio-economic development and national security and defense.