Ground level hinders construction progress of bridge on Tuyen Quang highway

Báo Giao thôngBáo Giao thông05/02/2025

Land acquisition problems are greatly affecting the construction progress of bridges on the Tuyen Quang - Ha Giang expressway.


Speaking to the press, a representative of the XL24 package management board of the Tuyen Quang - Ha Giang expressway project said they are very worried about the bridge construction progress because the site clearance problem has not been resolved.

Mặt bằng cản tiến độ thi công cầu trên cao tốc Tuyên Quang - Hà Giang- Ảnh 1.

Construction progress of the bridge on the Tuyen Quang - Ha Giang expressway is being greatly affected by land clearance problems.

Mr. Le Duc Tranh, Director of the Executive Board, said that in the last months of the year, the Project Management Board of Traffic Works of Tuyen Quang province, together with the district authorities, were also very determined to complete the handover of the project site.

In fact, up to this point, some critical road locations have not yet been handed over. Of these, 19/20 bridge locations have been handed over partial or full site clearance.

"According to the plan, by December 31, 2025, the entire Ha Giang - Tuyen Quang route will be completed, meaning there are only 10 months left to complete the works on the route.

However, up to now, critical road locations such as the Highway 2 overpass are stuck with the positions of all 4 pillars and cannot be implemented.

Or km54 bridge is a location with a large intersection but up to now the site has not been handed over to the contractor, the mobilization of machinery and people for construction is slowing down.

In February 2025, if the site locations are not cleared and not handed over to the contractor, the project will not be able to reach the finish line by the end of 2025," said Mr. Tranh.

Not only the main construction site, according to the leader of the package management board, site clearance work at material mines and waste dumps also encountered many obstacles when some households requested compensation levels higher than the local price frame.

For more information, the representative of the XL24 package management board said that within the scope of the handed over site, the joint venture contractor has mobilized 152 machines and equipment, 230 officers, engineers and workers to organize construction at 19/19 handed over bridge points.

Total output to date has reached about 174.5/626 billion VND, equivalent to nearly 31% of the plan.

The main items being focused on are: Bored piles at large bridges, clearing and cleaning the site, removing unsuitable materials, digging and filling roadbeds, constructing public roads, etc.

The Tuyen Quang - Ha Giang Expressway Project (Phase 1) has a total length of 77km, divided into 6 construction packages (from package XL19-XL24). This is a key transport infrastructure project, of great significance in improving inter-regional connectivity, promoting socio-economic development of Tuyen Quang province in particular and the Northern region in general.

In which, package XL24 includes 22 bridge works along the entire route.



Source: https://www.baogiaothong.vn/mat-bang-can-tien-do-thi-cong-cau-tren-cao-toc-tuyen-quang-ha-giang-19225020511311791.htm