Ho Chi Minh City - Moc Bai Expressway is over 51km long with a total investment of 19,617 billion VND - Photo: DUC PHU
On April 11, the Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board) reported to the Ho Chi Minh City People's Committee on the plan to start and complete traffic packages and works in April 2025, to celebrate the 50th anniversary of the Liberation of the South and National Reunification Day (April 30, 1975 - April 30, 2025).
In which, the Ring Road 2 project, section 1 from Phu Huu bridge to Vo Nguyen Giap street and section 2 from Vo Nguyen Giap street to Pham Van Dong street, will simultaneously start the bomb and mine clearance package.
In terms of scale, the project's 3.5km-long section 1 has a total investment of VND9,328 billion, while the 2.5km-long section 2 has a total investment of more than VND4,543 billion.
Also in April, the mine clearance package for the Ho Chi Minh City - Moc Bai Expressway will also begin construction. The project has a total length of more than 51km, with a total investment of VND19,617 billion, implemented under a BOT (build - operate - transfer) contract.
In phase 1, the Ho Chi Minh City - Moc Bai expressway will be invested with a scale of four lanes, and at the same time, construction works on the route, intelligent traffic system, toll collection system, rest stops... will be built to ensure synchronization and efficiency according to current standards and regulations.
Meanwhile, the Ho Chi Minh City Urban Infrastructure Construction Investment Project Management Board (Infrastructure Board) has just reported to the City People's Committee on the list of urban and flood prevention projects to start construction.
Specifically, package XL-03 of the project to dredge, improve the environment, and build infrastructure for Xuyen Tam canal will start construction on April 19.
The Xuyen Tam canal project is nearly 9km long from Nhieu Loc - Thi Nghe canal to Vam Thuat river, passing through Binh Thanh district and Go Vap district. The total investment capital for the project is 17,230 billion VND.
In addition, projects to upgrade irrigation works on the right bank of the Saigon River from Provincial Road 8 to Tra Canal (north of Tra Canal), and to improve the drainage system for the "flooding areas" of Nguyen Van Khoi and Le Van Tho streets (Go Vap District) will also start construction on April 19 and 25, respectively.
Which packages and projects will be completed before April 30?
Before April 30, a series of projects and packages were also opened to traffic by investors. Specifically, the Infrastructure Board will technically open some sections of packages XL-07, XL-08, XL-09 and XL-10 of the Tham Luong - Ben Cat - Nuoc Len canal renovation project.
The Traffic Department will open the road connecting Tran Quoc Hoan - Cong Hoa and connecting to T3 terminal; the project to upgrade and expand Duong Quang Ham street, the HC1 tunnel package at An Phu intersection...