Revealing the nearly 11,000 billion VND terminal of Tan Son Nhat airport

Báo Tiền PhongBáo Tiền Phong11/11/2024

TPO - After nearly two years of construction, Tan Son Nhat Airport's T3 terminal has been revealed with important items such as the roof, basements and above-ground floors, commercial area, overpass...


TPO - After nearly two years of construction, Tan Son Nhat Airport's T3 terminal has been revealed with important items such as the roof, basements and above-ground floors, commercial area, overpass...

Revealing the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 1

Terminal T3 of Tan Son Nhat airport with a total investment of nearly 11,000 billion VND is expected to be completed on April 30, 2025, 2 months ahead of schedule.

Revealing the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 2

When put into operation, the terminal will be the largest in the country with 20 million passengers, increasing the total capacity of Tan Son Nhat International Airport to 50 million passengers per year.

Revealing the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 3

According to the Project Management Board, all items of Tan Son Nhat T3 terminal have basically completed the structural part. Contractors are speeding up the construction progress of the architectural part and the remaining work.

Revealing the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 4

The most important part of the project is the 7,500-ton steel roof structure, which was completed in September after 120 days of progress. At the same time, the first-layer aluminum roof of the passenger terminal has also been built, covering 42,000 square meters, reaching 100%.

Revealing the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 5

The passenger waiting area, check-in counter and security check and screening areas have completed the structural frame.

Revealing the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 6

The viaduct system is under construction and is expected to be closed by the end of December and completed in February 2025.

Revealing the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 7

Workers are urgently installing glass walls on the passenger terminal floors with the goal of completing this item by the end of this year.

Revealing the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 8

The construction volume of the contractors will be divided into 15-day progress. The implementation process will be evaluated regularly. If any contractor fails to reach the specified output, they must compensate in the next 15-day period to ensure that the set target is always met.

Revealing the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 9

More than 90% of this work has been completed on the B2 floors of the commercial building, as well as the B1 and 1st floors of the passenger terminal.

Revealing the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 10

Contractors are actively deploying equipment and machinery systems for items such as air conditioning ducts, fire protection and water supply and drainage.

Revealing the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 11

The terminal has 90 traditional airline check-in counters, 20 automatic bagdrop counters and 42 check-in kiosks, 27 boarding gates (including 13 telescopic gates and 14 bus gates), 6 departure baggage handling islands and 10 arrival baggage return islands, and 25 security control gates.

Revealing the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 12
Revealing the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 13

The entire project has more than 2,500 engineers and construction workers, divided into many deployment teams to speed up construction progress.

Revealing the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 14

Along with the construction of the structure, equipment and machinery systems are also being imported for installation according to the progress of each item. Items with large volumes such as air conditioning ducts, fire protection, water supply and drainage have been installed over 90% on the B2 floors of the commercial building, B1 floors and 1 passenger terminal.

Revealing the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 15

Terminal T3 is expected to be completed two months ahead of schedule. Once operational, Terminal T3 will help reduce the load on the existing domestic terminal at Tan Son Nhat Airport.

Close-up of the 'huge' assets that Ms. Truong My Lan wants to get back
Close-up of the 'huge' assets that Ms. Truong My Lan wants to get back

Close-up of Phuoc Long bridge connecting District 7 with Nha Be district, nearing completion
Close-up of Phuoc Long bridge connecting District 7 with Nha Be district, nearing completion

Current status of the land renovated to extend Saigon River Park
Current status of the land renovated to extend Saigon River Park

Duy Anh



Source: https://tienphong.vn/lo-dien-nha-ga-gan-11000-ty-dong-cua-san-bay-tan-son-nhat-post1690466.tpo

Comment (0)

No data
No data

Same tag

Same category

Same author

No videos available