According to the Management Board of Investment and Construction of Agricultural and Rural Development Works (the investor), the Song Than reservoir project has completed the construction of the earth dam, deep discharge culvert combined with diversion, auxiliary dam 1, auxiliary dam 2, reservoir channel, reservoir flood avoidance road, management house, and fence. The concrete pavement and finishing work have not been completed yet due to the transportation of materials to the main dam construction... The total volume of construction and installation items of the project to date has reached 92%.
Comrade Trinh Minh Hoang, Vice Chairman of the Provincial People's Committee inspected the road project connecting Tan Son town to Ta Nang crossroads.
Regarding the road connecting Tan Son town to Ta Nang intersection project, the section from Tan Son town to Ma Noi commune has been completed and put into use since December 2023; the remaining section from Ma Noi commune to Ta Nang intersection has been constructed for about 9 km, and 14.9 km has not yet completed the work of collecting forest products and converting forest land. The total estimated completion value is 80% of the contract value for the sections with available land.
- Comrade Trinh Minh Hoang, Vice Chairman of the Provincial People's Committee inspected the progress of the Song Than reservoir project.
Through the actual inspection, the Vice Chairman of the Provincial People's Committee requested the investor of the Song Than reservoir project to proactively develop a specific implementation plan for each item; direct contractors to focus on human resources, urge to speed up the implementation progress; regularly monitor the construction process, ensuring the quality of the project. Along with that, the investor coordinates with the local authorities to urgently and thoroughly resolve 6 cases of undelivered land in the reservoir, striving to basically complete the water storage by mid-August this year. For the road connecting Tan Son town to Ta Nang intersection project, he requested the Department of Agriculture and Rural Development, forestry units and Ninh Son district to coordinate to review the current status, declare forest trees to develop a suitable plan to collect wood, avoid loss and waste, create favorable conditions for the construction unit to speed up the workload, promote the disbursement of allocated capital.