The "green lung" in the center of Da Nang officially started construction and renovation

After many postponements to find a solution and location to dump 100,000m3 of dredged mud if the largest lake in Da Nang, 29/3 Park, is constructed, on March 27, the Da Nang City government officially started the project to upgrade and renovate 29/3 Park, which is expected to be the "green lung" in the heart of the city.

Báo Công an Nhân dânBáo Công an Nhân dân27/03/2025

According to Mr. Le Quang Nam, Vice Chairman of Da Nang City People's Committee, 29/3 Park with an area of ​​up to 190,000m² (located at the corner of Nguyen Tri Phuong - Dien Bien Phu Street, Thanh Khe District, Da Nang) is a place for entertainment and community activities for residents and tourists.

Over time, many items in the park have become shabby and degraded. In particular, the wastewater system from residential areas surrounding the park is still discharged directly into the lake, causing pollution and greatly affecting the living environment here.

The
Delegates pressed the button to start the project to upgrade and renovate 29/3 Park, which is expected to become a "green lung" in the heart of Da Nang City.

Therefore, the project to upgrade and renovate 29/3 Park is of great significance to the people of Da Nang City. It not only has a special significance related to the field of cultural and social institutions, improving spiritual life, but also contributes to beautifying the city and creating a healthy and clean living environment for the community.

Since July 2023, the Da Nang City government has approved the investment policy to upgrade and renovate this park. And in the list of 38 projects committed to start construction in 2024, the project to renovate and upgrade 29/3 Park is expected to start construction in June 2024. However, due to the difficulty in finding a place to dump more than 100,000 m3 of dredged mud in the lake, the project to upgrade and renovate 29/3 Park has only officially started today.

The
During the implementation of the project to upgrade and renovate 29/3 Park, one of the important items is dredging and treating about 100,000m3 of mud in the lake.

According to the Management Board of Investment and Construction Projects for Civil, Industrial and Technical Infrastructure Works of Da Nang (investor): This is a Group B project, a level II technical infrastructure project with a total investment of nearly 673 billion VND from the city budget. Of which, the construction, equipment and other costs are 330 billion VND; the compensation costs are 297 billion VND; the contingency costs are 46 billion VND. The winning joint venture units including Dacinco - Nhat Huy - Dong Duong - Viet Anh Company will have to execute the construction bid; the project implementation period is expected to be 540 days (March 29, 2025 - September 30, 2026).

During the implementation of the project to upgrade and renovate 29/3 Park, one of the important items is dredging and treating about 100,000m3 of mud in the lake.

For a while, the relevant units had to struggle to find a place to dump the dredged sludge. Initially, the plan was to dump all the sludge at Khanh Son landfill, however, transporting the dredged sludge of the landfill project at Khanh Son Solid Waste Treatment Complex was not suitable. Draining the lake bed, then using an excavator combined with a truck to transport 100,000m3 of this sludge to the quarry of Phu My Hoa Company with a distance of 8.5km... the investor proposed the latest plan.

Source: https://cand.com.vn/Xa-hoi/la-phoi-xanh-giua-trung-tam-da-nang-chinh-thuc-duoc-khoi-cong-cai-tao-i763206/


Comment (0)

No data
No data

Same category

Check-in point of Ea H'leo wind farm, Dak Lak causes a storm on the internet
Images of Vietnam "Bling Bling" after 50 years of national reunification
More than 1,000 women wearing Ao Dai parade and form a map of Vietnam at Hoan Kiem Lake.
Watch fighter jets and helicopters practice flying in the sky of Ho Chi Minh City

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product