According to the proposal of the Provincial Traffic Construction Investment Project Management Board, the source of fill soil will be coordinated for Tan Nam Construction Joint Stock Company with a volume of 100 thousand m3 and Thanh Phat Construction Company Limited with a volume of 90 thousand m3.
Currently, the demand for fill soil for the construction of the Ring Road 3 Project - Ho Chi Minh City is about 456 thousand m3. The total volume of fill soil brought to the construction site is about 46 thousand m3, reaching 10% of the total demand.