No power shortage during peak dry season and throughout 2025

On April 23, Prime Minister Pham Minh Chinh signed Official Dispatch No. 49/CD-TTg on drastic, synchronous and effective implementation of solutions to ensure electricity supply during peak periods in 2025 and the coming time.

Báo Công an Nhân dânBáo Công an Nhân dân23/04/2025

The telegram emphasized that firmly ensuring national energy security and adequate electricity supply are among the fundamental and decisive factors for successfully implementing the country's socio -economic growth goals.

In order to promptly meet electricity demand during peak months of 2025 (May, June, July) and the coming time, ensuring no power shortage in any case, the Prime Minister requested the Minister of Industry and Trade to urgently organize the implementation of the adjusted Power Plan VIII, promptly issue the Plan to implement the adjusted Power Plan VIII, to implement the goals and tasks set out in the plan, to be completed before May 10.

The Minister of Industry and Trade is fully responsible to the Government and the Prime Minister for ensuring adequate electricity supply to serve production and business activities and people's lives.

The Prime Minister also requested the Minister of Industry and Trade to direct the strengthening of inspection and supervision of the operation and urging the implementation of power source projects, to best prepare for power generation during peak months.

No power shortage during peak dry season and the whole year 2025 -0
The Government directs to focus on comprehensive solutions to ensure electricity supply.

Regarding power source projects, the Ministry of Industry and Trade needs to focus on directing the acceleration of the implementation of important national projects and key energy sector projects that are included in the planning. In particular, urgently put Nhon Trach 3 Thermal Power Plant into operation in June 2025; Nhon Trach 4 Thermal Power Plant into operation in August 2025; connect Unit 1 of Quang Trach 1 Thermal Power Plant to the grid before September 2; put Unit 1 of Hoa Binh Hydropower Plant expansion project into operation in August 2025, Unit 2 into operation in October 2025.

Regarding power transmission projects, the Ministry of Industry and Trade needs to focus on ensuring the progress of transmission projects, implementing urgent solutions on transmission, purchasing electricity from abroad, such as the Lao Cai - Vinh Yen 500kV transmission line project, the Hai Phong - Thai Binh 500kV transmission line projects, and Than Uyen - Lao Cai to ensure completion before September 2.

The Minister of Agriculture and Environment (MARD) is assigned to preside over and closely coordinate with relevant ministries, agencies and localities, direct owners of hydroelectric reservoirs to calculate and make specific plans to take water from hydroelectric reservoirs to serve agricultural production, in which priority is given to reserving maximum reserve water for power generation during peak times, and enhancing solutions for water saving.

The Minister of Finance directs and supervises EVN, TKV, and PVN to strengthen effective coordination, organize and well implement contracts for electricity purchase and sale, coal supply, and gas supply, all for the common goal, for the national interest, to prevent negativity, corruption, and waste; take responsibility for leadership and direction of stable operation and quick resolution of incidents (if any) for power sources of EVN, PVN, and TKV...

Source: https://cand.com.vn/Xa-hoi/khong-de-thieu-dien-cao-diem-mua-kho-va-ca-nam-2025-i766114/


Comment (0)

No data
No data

Same category

Follow the sun
Come to Sapa to immerse yourself in the world of roses
Wildlife on Cat Ba Island
The fiery red sunrise scene at Ngu Chi Son

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product