In the document, the Chairman of Lao Cai Provincial People's Committee requested agencies and units to continue mobilizing the entire political system to participate, resolutely direct the implementation of site clearance and support investors during construction; strengthen propaganda and mobilization work to gain consensus and support from people in the project area.
The People's Committees of Bao Thang and Bao Yen districts urgently complete the site clearance work of the route corridor in the province and hand it over to the Power Project Management Board 1 before April 20, 2025 for construction implementation; including the payment of compensation costs to 31 households, and at the same time, promptly stabilize new housing better than the old housing for 38 resettlement cases.
For the construction of public roads, the People's Committees of Bao Thang and Bao Yen districts closely coordinate with the Power Project Management Board 1 and the construction contractor to resolve difficulties and problems during the implementation process.
The Chairman of Lao Cai Provincial People's Committee requested the Power Project Management Board 1 to urge the contractor to construct all pole positions (currently, only 72/100 poles have been constructed, 28 poles have not been constructed yet)./.
Source: https://baophapluat.vn/khan-truong-hoan-thanh-giai-phong-mat-bang-hanh-lang-du-an-duong-day-500kv-lao-cai-vinh-yen-truoc-ngay-2042025-post545521.html