On the morning of September 1, Prime Minister Pham Minh Chinh inspected the construction progress of key transport projects in Da Nang City.
At the Lien Chieu Port construction investment project - Shared infrastructure, the Prime Minister presented gifts to encourage engineers and construction workers.
Reporting to the Prime Minister, Mr. Le Thanh Hung, Director of the Management Board of Priority Infrastructure Investment Projects in Da Nang (investor) said that the project was implemented by the Consortium of Phu Xuan Consulting and Construction Joint Stock Company - Lung Lo Construction Corporation - Truong Son Construction Corporation - DACINCO Construction Investment Company Limited - Xuan Quang Construction Joint Stock Company.
The value of completed construction volume to date has reached 67.31%. Specifically, the construction of the dyke and breakwater has reached 66.1%; the dredging of the shipping channel and water area has reached 66.8%; the construction of the road and drainage has reached 68.4%.
Mr. Hung added that according to Resolution No. 136/2024/QH15 dated June 26, 2024 of the National Assembly on the organization of urban government and piloting a number of specific mechanisms and policies for the development of Da Nang city, the investment in the construction of the overall Lien Chieu seaport project has an investment capital of VND 45,000 billion or more, belonging to the list of priority industries, occupations, and projects to attract strategic investors to the city.
"Currently, the Board is coordinating with the Department of Planning and Investment, the Department of Transport and the consulting unit to complete the pre-feasibility study report to submit to central ministries and branches for appraisal and submission to the Prime Minister for approval, as a basis for selecting investors according to regulations," said Mr. Hung.
According to Prime Minister Pham Minh Chinh, the project was implemented very quickly, after 1 year of both investment procedures and construction.
The Prime Minister requested that these results be promoted, with greater speed, efficiency, determination, effort and determination.
The Prime Minister also agreed with the proposals for planning Da Nang seaport and requested a master plan, with investment being phased in. At the same time, traffic connections should be promoted to attract investment.
Around noon the same day, the Prime Minister inspected the Da Nang - Quang Ngai expressway interchange, the Hoa Lien - Tuy Loan expressway project with National Highway 14B (Hoa Vang district). This interchange is expected to have an investment of about 400 billion.
Here, the Prime Minister directed to separate the project into an independent one, and build a different level intersection. At the same time, Da Nang was assigned as the project investor. Da Nang will cover 50% of the cost, and the Central Government will support 50%.
The investment project to build Lien Chieu Port in Da Nang City - shared infrastructure has a total investment of 3,426 billion VND, including main items: Embankment and breakwater; Channel and water area; Traffic road connecting to the port gate, scale of 6 lanes; Technical infrastructure for electricity supply, water supply and synchronous auxiliary works to the gate of the starting port area.
Of which, the construction contract package has a contract value of VND 2,945 billion (including VAT and contingency fees).
The contract performance period is 1,380 days (including 1,080 days of performance and 300 days of completion of legal procedures related to the contract). The contract performance start date is December 14, 2022.
Source: https://www.baogiaothong.vn/thu-tuong-day-manh-ket-noi-giao-thong-de-keu-goi-dau-tu-vao-cang-bien-da-nang-192240901115223898.htm