Mr. Nguyen Tam Thinh - Chairman of the Board of Directors of Trung Nam Construction Investment Joint Stock Company (Trung Nam Group) - has just signed a document to send to the Central Party Office and the Government Office regarding the biggest problem of the Project to Solve Flooding Due to Tides in Ho Chi Minh City Area Considering Climate Change Factors (Phase 1).

This 10,000 billion VND flood prevention project, invested by Trung Nam Group, started on June 26, 2016 but has yet to reach its completion.

w cong phu xuan vnn 1 1 1281 (1).jpg
The VND10,000 billion flood prevention project in Ho Chi Minh City still has no completion date after 8.5 years of construction. Photo: Hoang Giam

According to Trung Nam Group, the project completed more than 90% of the volume in 2020, then paused so that the Ho Chi Minh City People's Committee could propose to the Government to remove legal obstacles.

Then, the Government issued Resolution 40/NQ-CP dated April 1, 2021. According to the Resolution, the content of the inappropriate payment method in the BT contract of the project is mentioned in Article 1 and the directive clearly states: "This issue is the responsibility of the Ho Chi Minh City People's Committee and related organizations and individuals".

Trung Nam Group said that since the Government issued Resolution 40, although the investor has reported many times, the Ho Chi Minh City People's Committee has not yet adjusted the BT contract to realize the Government's direction. In recent reports, the city is still recommending to the Government that the proposed content is not consistent with the content of Resolution 40.

"The payment method of the project has been specifically directed in Notice No. 285/TB-CP dated August 20, 2015 of the Government Standing Committee: "Applying the form of construction - transfer (BT) payment by land fund, in case the value of the land fund payment is less than the value of the BT project, the People's Committee of Ho Chi Minh City is paid by the city budget for the difference.

This is the first and biggest problem that needs to be resolved to remove the project's bottleneck, so that other related legal procedures can continue to be implemented" - Trung Nam Group's document stated.

Therefore, investors hope to receive support from central agencies so that the project can be re-implemented, completed and put into operation soon.

At the same time, the enterprise requested that Ho Chi Minh City pay attention to and remove obstacles for the project in accordance with the contents of Resolution 40, Notice No. 285/TB-CP and current legal regulations.

w cong phu dinh vnn 2 1 1304 (1).jpg
Investors hope to have their problems resolved so that the 10,000 billion VND flood prevention project can be restarted soon. Photo: Hoang Giam

Previously, in mid-December 2024, the Government Office issued a document conveying the Prime Minister's opinion on focusing on removing obstacles for the above-mentioned flood prevention project.

In particular, the Prime Minister requested the Minister of Planning and Investment, the Governor of the State Bank and the Chairman of the Ho Chi Minh City People's Committee to urgently and seriously implement the instructions in Document No. 9050/VPCP-NN dated December 9.

The Prime Minister also requested the Chairman of the Ho Chi Minh City People's Committee to proactively work with the Ministry of Planning and Investment and relevant agencies to urgently propose solutions to handle the project's problems and report before December 20.

In addition, the Prime Minister requested the Standing Committee of the Ho Chi Minh City Party Committee to direct and urge the City People's Committee and relevant agencies to focus on thoroughly resolving the project's problems.

Prime Minister requests urgent removal of obstacles for 10,000 billion VND flood prevention project

Prime Minister requests urgent removal of obstacles for 10,000 billion VND flood prevention project

The Prime Minister requested the Minister of Planning and Investment, the Governor of the State Bank and the Chairman of the Ho Chi Minh City People's Committee to urgently and seriously implement the Prime Minister's direction on removing obstacles for the 10,000 billion VND flood prevention project.
Ho Chi Minh City Chairman informs about 10 trillion VND flood prevention project, metro line 1

Ho Chi Minh City Chairman informs about 10 trillion VND flood prevention project, metro line 1

The Chairman of Ho Chi Minh City said that the central government's leaders cited the 10 trillion VND flood prevention project as a typical example of waste and asked the city to focus on removing obstacles in December.
Ho Chi Minh City reports to the National Assembly about the 10,000 billion VND anti-flooding project

Ho Chi Minh City reports to the National Assembly about the 10,000 billion VND anti-flooding project

The 10,000 billion VND flood prevention project of Ho Chi Minh City is facing many difficulties and obstacles due to lack of capital to complete it, and is currently more than 7 years behind schedule.