Latest images of the nearly 11,000 billion VND terminal of Tan Son Nhat airport

Báo Tiền PhongBáo Tiền Phong18/09/2024


TPO - The T3 terminal project at Tan Son Nhat International Airport has now reached 70% of the total volume. The Project Management Board said there are about 200 days left to "sprint" to put the project into operation and exploitation on April 30, 2025.

Latest images of the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 1
In mid-September 2024, it rained continuously in Ho Chi Minh City, but at the construction site of the T3 terminal project - Tan Son Nhat International Airport, about 2,500 workers and engineers were still working day and night "3 shifts, 4 shifts" to put the project into operation on April 30, 2025.
Latest images of the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 2

According to Vietnam Airports Corporation (ACV, the investor), currently in the rough concrete structure part, the main items such as passenger terminal, multi-storey parking garage combined with non-aviation services, electromechanical building, aircraft parking lot... are all over 85% complete, with some items 100% complete.

Latest images of the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 3
In terms of architectural finishing, the steel roof structure has completed 7,500 tons (100%); the aluminum roof with a total volume of 60,000m2 has been 100% completed, and the glass curtain wall is expected to be completed on December 22 this year.
Latest images of the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 4
The station's stone floor is also expected to be completed on December 22. The ceiling construction will begin on September 15, 2024 and is expected to be completed on January 29, 2025.
Latest images of the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 5
Electromechanical systems, elevators, escalators, bridge bridges, and baggage conveyors have all been completed or are in the final stages.
Latest images of the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 6
Mr. Le Khac Hong, Head of the T3 Terminal Project Management Board, said that after more than a year of construction of package No. 12 (construction and installation of equipment for T3 Terminal), the concrete part of the terminal body has been completed since April 30, and the iron structure of the terminal reached 100% volume on September 2, shortening the progress by 2 months. This is a prerequisite to continue shortening the progress of other items.
Latest images of the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 7
"The overall progress of the project has reached 70% of the workload and will be completed on March 30, 2025.
To inaugurate the project on April 30, 2025, the project must be completed 1 month earlier, meaning there are only 200 days left to complete the project. In the coming time, we will continue to thoroughly implement the Prime Minister's directive for key projects, which is "overcoming the sun and rain, eating and sleeping quickly, working in 3 shifts, working through holidays, Tet, and days off, and only discussing work and not backtracking" - Mr. Le Khac Hong said.
Latest images of the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 8

According to the Project Management Board, the investor and contractors have continuously launched competitions to ensure progress. After two successful competitions, on September 17, the investor decided to continue launching the third competition "90 days and nights to complete the entire station roof, facade and power the project".

Latest images of the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 9
This competition mainly focuses on completing items such as the entire station roof and auxiliary works; completing all the building's facade glass, floor tiling work...
Latest images of the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 10Latest images of the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 11Latest images of the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 12Latest images of the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 13

2,500 workers and engineers are working day and night with the spirit of "overcoming the sun and rain", working "3 shifts, 4 shifts" to put the T3 terminal into operation on April 30, 2025.

Latest images of the nearly 11,000 billion VND terminal of Tan Son Nhat airport photo 14

The T3 Passenger Terminal Construction Project - Tan Son Nhat International Airport includes 4 main items: Passenger terminal, high-rise parking garage combined with non-aviation services, overpass system in front of the terminal and aircraft parking lot with a total investment of 10,990 billion VND. The capital to implement the project is mobilized from the equity capital of Vietnam Airports Corporation - JSC and commercial loans.

ACV said that the construction of passenger terminal T3 - Tan Son Nhat International Airport aims to ensure the following goals: Investing in the construction of passenger terminal T3, with a capacity of 20 million passengers/year and synchronous auxiliary works, serving domestic exploitation at Tan Son Nhat International Airport to meet exploitation requirements, in accordance with the planning and division of exploitation output between Long Thanh airport and Tan Son Nhat airport, reducing the load on the currently overloaded terminal T1, improving the quality of passenger service .

Image of the last pedestrian bridge connecting Thu Duc station just completed
Image of the last pedestrian bridge connecting Thu Duc station just completed

HCMC: Local congestion on the first morning of Phu Huu BOT toll collection
HCMC: Local congestion on the first morning of Phu Huu BOT toll collection

Heavy rain from storm Yagi, the South welcomes high tide and risk of severe flooding
Heavy rain from storm Yagi, the South welcomes high tide and risk of severe flooding

Ho Chi Minh City and the South are about to have very heavy rain.
Ho Chi Minh City and the South are about to have very heavy rain.

Heavy rain in Ho Chi Minh City and the South during the weekend
Heavy rain in Ho Chi Minh City and the South during the weekend

Huynh



Source: https://tienphong.vn/hinh-anh-moi-nhat-ve-nha-ga-gan-11000-ty-dong-cua-san-bay-tan-son-nhat-post1674213.tpo

Comment (0)

No data
No data

Same tag

Same category

Luc Yen, a hidden green gem
Spreading national cultural values ​​through musical works
Lotus color of Hue
Hoa Minzy reveals messages with Xuan Hinh, tells behind-the-scenes story of 'Bac Bling' causing global fever

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product