Land clearance of National Highway 14E
Speeding up the progress of site clearance and construction of key projects, including the project to renovate and upgrade National Highway 14E through Hiep Duc, is a priority task for the district to focus on and implement vigorously in the first quarter.
Mr. Le Viet Dinh - Director of the Board of Construction Investment and Land Fund Development of Hiep Duc district said that as of April 8, the district had approved 51 compensation plans for damages and site clearance for 1,488 households with a budget of VND 86.09 billion; VND 85.133 billion had been disbursed, reaching 89.6%.
The remaining volume that has not been cleared includes 6 households in Binh Lam commune, 3 households in Que Tho commune, and 23 households in Tan Binh commune. There are 8 new households in Song Tra commune due to design adjustments but there are no problems with construction because there is an agreement with the people.
“Currently, we are focusing on promoting and explaining resettlement policies so that people agree with the plan. In general, the current site basically ensures that investors can implement the project smoothly,” said Mr. Dinh.
Ms. Nguyen Thi Le Tham - Secretary of the Party Committee of Song Tra commune said that thanks to the handover of 100% of the land, the construction progress of the National Highway 14E project through the area has been accelerated compared to many other localities. Recently, the contractor has focused on human resources and specialized machinery and equipment to pave asphalt concrete, creating favorable travel conditions for people.
“The National Highway 14E project through Song Tra commune is 9.77km long. Up to now, the construction unit has completed paving the section from Thanh Nien bridge to the commune People's Committee for more than 3km and is speeding up the progress of the remaining sections. The sections that have been paved, people are very excited because they see the road is wider and cleaner than before” - Ms. Tham shared.
An executive officer of the project management unit (Project Management Board 4, Vietnam Road Administration) said that taking advantage of the sunny weather, the joint venture contractor for the Hiep Duc - Phuoc Son section is concentrating equipment and human resources to carry out construction on the entire route, creating favorable conditions for people to travel.
However, there is still a situation of "leopard skin" land acquisition in some locations and the electricity and telecommunications systems have not been relocated, causing difficulties and affecting construction progress.
In addition to the National Highway 14E project, Hiep Duc district is also focusing on removing obstacles in the site clearance work for the ring road project from lane 3 Gia Bang (Tan Binh town) to the center of Que Luu commune; Tan Binh bridge project and the National Highway 14E bypass through Tan Binh town; and resettlement area projects along the northern ring road (Tan Binh town).
Recently, the People's Committee of Hiep Duc district has issued a document reporting and asking for opinions from the Provincial People's Committee to remove difficulties and obstacles in compensation, support and resettlement for each specific case of each of the above projects.
Key tasks
The Standing Committee of Hiep Duc District Party Committee has just held the 21st Conference of the District Party Executive Committee (term IX, term 2020 - 2025) to evaluate the leadership situation in implementing the tasks of the first quarter and key tasks of the second quarter of 2025.
According to the report, in the first quarter of 2025, Party committees, authorities, the Vietnam Fatherland Front, and socio -political organizations will focus on leading, directing, and organizing the good implementation of tasks according to resolutions, programs, and plans.
The socio -economic situation in the district continues to grow well. The total state budget revenue in the area is over 267.9 billion VND, reaching 43.3% of the estimate assigned by the province. Of which, the revenue generated by the economy is over 31.2 billion VND, reaching 36.6% of the target assigned by the province.
The work of building the Party and the political system has been strengthened. The district has consolidated and rearranged the organizational apparatus, perfected the leadership and management positions of a number of Party committees, agencies and units; consolidated, rearranged and perfected the model of grassroots Party organizations according to the policy of rearranging the political system.
Up to now, Hiep Duc has 39 grassroots party organizations under the District Party Committee with 2,013 party members. In the first quarter, 6 party members were admitted (reaching 9.5% of the resolution); 5 comrades were officially recognized as party members; 82 cases were transferred to party activities; 18 party badges of various types were proposed to be awarded on February 3, 2025...
At the 21st District Party Executive Committee Conference, delegates focused on discussing the content of the reports, especially focusing on solutions to synchronously and effectively implement socio-economic development, national defense and security goals in the second quarter.
Accordingly, the district continues to deploy and effectively implement economic development programs, build new rural areas, civilized urban areas, develop mountainous areas, and speed up site clearance progress for key projects.
At the same time, focus on implementing well the work of arranging commune-level administrative units according to the roadmap, ensuring synchronization, political and social stability, and suitability with development practices...
In addition, Hiep Duc focuses on developing party members, improving the quality and effectiveness of political and ideologicaleducation , monitoring and grasping information, forecasting the situation and promptly orienting public opinion, especially before, during and after the implementation of administrative unit rearrangement at all levels and the organization of Party congresses (term 2025 - 2030).
Hiep Duc completed construction and repair of 26 temporary and dilapidated houses.
On April 15, the Steering Committee for the work of eliminating temporary and dilapidated houses in Hiep Duc district in the period of 2023 - 2025 held a meeting to deploy tasks.
According to the plan, in 2025, the total number of temporary and dilapidated houses in Hiep Duc district that need to be built is 93 (63 new houses, 30 houses repaired). Up to now, 25 new houses have been completed and 1 house has been repaired. From now until October 2025, there are 38 new houses and 29 houses that need to be repaired to be completed.
In particular, the district prioritizes completing housing support for people with revolutionary contributions and martyrs' relatives before July 27. Up to now, the total socialized funding for eliminating temporary housing has reached more than 553 million VND . (TAM DAN)
Handing over solidarity houses to poor households in Phuoc Gia commune
Hiep Duc district has just coordinated with Cam My district (Dong Nai province) to organize the acceptance and handover of a solidarity house to Mr. Ho Van Nam (Phuoc Gia commune). Mr. Nam is a poor household with difficult circumstances in the locality.
Mr. Nam's house was completed after nearly 2 months of construction with a total cost of 130 million VND, of which Cam My district supported 80 million VND; the family contributed and the community contributed 50 million VND in working days.
At the handover ceremony, the leaders of Hiep Duc district thanked the leaders of Cam My district for supporting the construction of houses for poor households in the district, thereby contributing to the locality's goal of eliminating temporary and dilapidated houses in the district. (VINH ANH)
Administrative procedure records resolved on time reached 98.4%
Hiep Duc District People's Committee said that in the first quarter of 2025, administrative reform, digital transformation and Project 06 were implemented by agencies, units and localities in the area with many effective solutions.
In particular, the district completed digitizing civil status data, focusing on implementing the 90-day peak period of database construction according to Plan No. 1643 of the Provincial People's Committee.
From December 15, 2024 to March 25, 2025, the total number of administrative procedure records received at the district and commune levels was 1,701 records, of which the rate of records resolved on time (including records resolved and being resolved) reached 98.41%; the rate of online payment reached 72.5% . (VINH ANH)
Source: https://baoquangnam.vn/hiep-duc-tap-trung-giai-phong-mat-bang-du-an-trong-diem-3153027.html
Comment (0)