A series of major traffic projects such as Tu Lien Bridge, Ngoc Hoi Bridge, Tran Hung Dao Bridge and component project 3 of Ring Road 4 - Capital Region are all expected to start construction in the second quarter of 2025...
The Hanoi Transport Construction Investment Project Management Board has just announced the progress of key projects in Hanoi.
Specifically, with component project 1.1, the Ring Road 4 - Capital Region project (land clearance in Hanoi) was adjusted by the City People's Committee to the end of the second quarter of 2025.
Contractor implementing the construction of the parallel road to Ring Road 4 - Capital Region.
In 2024, the Board coordinated with districts to clear 98.44% of the land plan; completed technical infrastructure for 13/13 resettlement areas and arranged resettlement for 337/818 households.
Soc Son, Me Linh, Dan Phuong, and Hoai Duc districts are moving underground and above-ground structures. Other localities are designing and selecting contractors.
Component project 2.1 builds parallel roads (urban roads), has basically completed the construction of roadbed, embankment and crushed stone grading for sections that do not require foundation treatment... The output is about 43.04% of the contract value, striving to complete the entire route in the fourth quarter of 2025.
Component project 3 (expressway construction investment under the public-private partnership method) has completed the preparation of bidding documents and issued bidding documents on November 6, 2024; expected bid opening on February 5, 2025.
With the project to renovate and upgrade National Highway 6, Ba La - Xuan Mai section, the Investor is urging to focus on 3 bid packages in Chuong My district. The two bid packages in Ha Dong district are completing procedures, striving to start construction in the first quarter of 2025.
With the underpass project at the intersection of Ring Road 2.5 and Giai Phong Road, construction is on schedule and will be completed in 2025.
The Van Phuc Bridge project is implementing procedures to select a construction contractor, striving to start construction in the second quarter of 2025...
In addition, the Board has coordinated with departments, branches and localities to establish and submit for appraisal the investment policies of 12 projects; approved the investment policies of 2 projects (underpass at the intersection of Me Tri - Duong Dinh Nghe - Ring Road 3 and at the intersection of Tay Thang Long - Ring Road 3)...
In 2025, the Hanoi City Traffic Construction Investment Project Management Board strives to disburse 95% of the assigned capital plan; implement the Ring Road 4 - Capital Region project to ensure quality, progress and safety; and plans to start construction of 12 projects. Of which, Tu Lien Bridge, Ngoc Hoi Bridge, Tran Hung Dao Bridge are expected to start construction in May 2025; Component Project 3 of Ring Road 4 - Capital Region will start construction in the second quarter of 2025...
At the conference to summarize the work in 2024 and deploy the tasks in 2025 of the Hanoi Traffic Construction Investment Project Management Board, which took place recently, Mr. Duong Duc Tuan - Vice Chairman of the Hanoi People's Committee requested the Board to speed up the progress of key projects, especially traffic projects that have completed investment procedures. Improve the capacity of project management and operation and update and apply new technologies in supervision, ensuring progress, quality and safety. At the same time, it is necessary to pay attention to coordinating more closely with departments, branches, sectors and localities to remove bottlenecks and create favorable conditions for contractors to construct projects...
Source: https://www.baogiaothong.vn/ha-noi-khoi-cong-loat-du-an-giao-thong-lon-trong-nam-2025-192250112060745545.htm