Completed 60 % of contract value
In late August 2024, Giao thong Newspaper reporters were present at the construction site of the Southern Ring Road project in Thai Binh City and recorded that on many sections of the route such as at the S1 cross-bridge (Tu Tan commune, Vu Thu district), the section through Song An commune, Kien Giang bridge (Vu Chinh commune, Thai Binh city)... many equipment and machinery were gathered, hundreds of officers and technical workers were present and working hurriedly.
Asphalt concrete contractor at Km5, Trung An commune, Vu Thu district.
The Southern Belt Road Project of Thai Binh City, from the S1 bridge to the extended Chu Van An Street, has a total length of 8.37km, starting at the intersection with National Highway 10 at Km 59+950, in Tu Tan Commune (Vu Thu District), and ending at the intersection with Chu Van An Street, in Vu Chinh Commune (Thai Binh City).
The route is designed as a level II traffic project; maximum speed is 80km/h, road width is 20.5m. The total investment of the project is nearly 1,039 billion VND, from the central budget, provincial budget and other legal sources.
The project started on May 8, 2022 and is scheduled to be completed by October 24, 2024.
Clip: Asphalt concrete contractor at Km5, Trung An commune, Vu Thu district.
Up to now, the entire Southern Belt Road of Thai Binh City, from the S1 bridge to Chu Van An Street, has been almost completed. Some sections have been paved with asphalt concrete. The contractor is focusing on implementing the electrical system, drainage, hard railings, and trees.
Speaking with Giao thong Newspaper reporters, Mr. Nguyen Trong Vinh, Director of the Project Management Board (PMU) for investment and construction of traffic works in Thai Binh province, said that up to now, the value of the project's construction and installation volume is estimated at 480/776 billion VND, reaching about 60% of the contract value.
The contractor has completed the construction of the road section up to the K98 sand layer: 8.05/8.37km. The construction has completed the crushed stone layer of 7.25/8.37km and the contractor is currently laying asphalt concrete.
The hard railing system of the Southern Beltway Project of Thai Binh City, from S1 Bridge to Chu Van An Street is being deployed by the contractor.
The main structure of Kien Giang Bridge has been completed; S1 Cross Bridge is currently being constructed to fill the abutment bed, abutment cones and retaining walls.
Focus on removing the "bottleneck" of land acquisition and clearance
The project's site clearance work has been basically completed, with only about 0.32km remaining in Vu Thu district related to resettlement. The Project Management Board is coordinating with the Vu Thu District People's Committee to focus on site clearance to hand over to the contractor to construct the project on schedule.
Mr. Nguyen Huy Son, Deputy Site Commander, representative of the construction contractor (Joint Venture of Thang Long Import-Export Joint Stock Company - Bridge Construction Joint Stock Company 75 - Joint Stock Company 873 for traffic construction) said that according to the contract, the project must be completed by October 24, 2024 to hand over to the investor.
S1 cross bridge in Tu Tan commune, Vu Thu district.
However, up to this point, there is still about 0.32km of land still stuck, the unit is coordinating with the investor and the People's Committee of Vu Thu district to handle land acquisition. When the land is handed over, the unit will focus on human resources to deploy construction, striving to ensure the proposed progress.
"On the handed-over site, up to this point, the contractor has basically completed the main tasks, has paved 2.5km of asphalt, and is completing the green trees and lighting items. On the route, there are 2 bridges, Cau Ngang S1 and Kien Giang Bridge, which are basically completed, just waiting for the road to be opened to pave the bridge surface. If the entire route is handed over, the unit will strive to complete it on schedule," said Mr. Son.
Ms. Pham Thi Nhu Phong, Chairwoman of Vu Thu District People's Committee, said that the Southern Belt Road project of Thai Binh City (from S1 bridge to extended Chu Van An street) is one of the province's key projects. The section passing through Vu Thu District includes Vu Thu town, Tu Tan commune, Hoa Binh commune, Song An commune and Trung An commune with a length of 6.2km.
The contractor is planting trees and installing lighting systems along the route.
As soon as the project was deployed, the district took drastic measures, issued documents to thoroughly grasp and direct the implementation of site clearance work; held weekly meetings to listen to reports on the project's site clearance progress.
Strengthening the direction of communes and towns to issue specialized resolutions, establish steering committees and working groups of communes, mobilizing the entire political system to create a combined strength to propagate and mobilize people to implement the land acquisition and clearance policy.
The District People's Committee assigned the Center for Land Fund and Industrial Cluster Development and the People's Committees of communes and towns to develop a detailed plan for site clearance for each household, clearly stating the difficulties, problems, causes, solutions and specific implementation time.
The progress of the resettlement area is being urgently implemented so that people can hand over the site to the construction contractor.
Along with that, regularly follow up on difficult and problematic cases, assign specific tasks to leaders of the District People's Committee, departments, offices, and specialized agencies to meet directly with households to dialogue, explain, propagate, and mobilize each household.
According to Ms. Phong, some remaining sections are mainly due to land areas in Tu Tan, Hoa Binh, Song An communes as well as the progress of resettlement area implementation. Currently, the resettlement area has been completed.
"With high political determination, Vu Thu district is taking drastic action, focusing the entire political system on implementing site clearance at some of these remaining sites as soon as possible," Ms. Phong affirmed.
Source: https://www.baogiaothong.vn/go-nut-that-de-du-an-duong-vanh-dai-phia-nam-tp-thai-binh-som-ve-dich-192240901085337521.htm