Removing bottlenecks in site clearance for Tuyen Quang - Ha Giang expressway project

Việt NamViệt Nam22/06/2024


The Provincial Traffic Construction and Investment Project Management Board worked with the People's Committee of Ham Yen district on site clearance for the Tuyen Quang - Ha Giang expressway project.

The Tuyen Quang - Ha Giang expressway through Ham Yen district is more than 48km long with over 1,700 households subject to site clearance, of which 321 households must relocate their houses.

According to the report of Ham Yen District People's Committee, by June 21, 2024, the district had cleared 75% of the recovered land area, handing over 35km2 to the construction unit. The district is implementing 19 resettlement areas for people subject to land recovery in 11 communes and towns; 2/3 of the district's resettlement areas have reached 70% progress.

However, the land acquisition and clearance work is currently facing some difficulties for households that have not received compensation, mainly due to relocation of houses and not being able to arrange resettlement, related to building houses on agricultural land; 227,661 forest land, land in joint venture with forestry enterprises, difficulty in determining the origin of the land, and disagreement with the compensation price.

At the meeting, delegates heard about the difficulties, obstacles and recommendations in the land acquisition work of 83 households who have not received compensation for the recovered area, and the causes of obstacles of each household. At the same time, they discussed solutions for implementation in the coming time with the goal of properly implementing the policy, not letting people suffer and clearing the entire route of land acquisition in the district.

Accordingly, the solutions proposed by the People's Committee of Ham Yen district are to continue to carry out the propaganda work on legal policies on compensation and site clearance; review the entire area of ​​agricultural land within the site clearance area to mobilize people not to put it into production for the 2024 winter-spring crop.

At the same time, speed up the construction progress of resettlement areas, striving to complete 10/19 resettlement areas to accommodate households by the end of July 2024. Ham Yen district commits to basically resolve the bottlenecks in site clearance for the Tuyen Quang - Ha Giang expressway project through the district by July 30, 2024.



Source: https://baotuyenquang.com.vn/go-diem-nghen-giai-phong-mat-bang-du-an-cao-toc-tuyen-quang-ha-giang-193937.html

Comment (0)

No data
No data

Same tag

Same category

Developing community tourism in Ha Giang: When endogenous culture acts as an economic "lever"
French father brings daughter back to Vietnam to find mother: Unbelievable DNA results after 1 day
Can Tho in my eyes
17-second video of Mang Den so beautiful that netizens suspect it was edited

Same author

Image

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product