This morning, October 27, Standing Vice Chairman of the Provincial People's Committee Ha Sy Dong had a working session with Vinh Linh District People's Committee, Quang Tri Forest Products Joint Stock Company and related departments and branches on resolving difficulties in site clearance (GPMB) for Quang Tri Forest Products Joint Stock Company affected by the Van Ninh - Cam Lo section project of the North - South Eastern Expressway construction project in the 2021 - 2025 period.
Permanent Vice Chairman of the Provincial People's Committee Ha Sy Dong concluded the working session - Photo: LA
According to the report of Vinh Linh District People's Committee, in carrying out site clearance work to implement the Van Ninh - Cam Lo expressway component project, the District People's Committee mobilized Quang Tri Forest Products Joint Stock Company (the company) to dismantle all assets and move machinery out of the site clearance area, however, the company did not hand over the site to the construction unit to implement the project.
After many attempts to persuade and persuade the company but the company did not cooperate, from October 24 to 25, Vinh Linh District People's Committee organized to forcibly reclaim the company's land. By 3:00 p.m. on October 25, the enforcement was completed and the last 200 meters of the main route were handed over to the Ho Chi Minh Road Project Management Board for project construction. The enforcement ensured absolute safety for people and property.
Regarding compensation and support, the District People's Committee has fully implemented it in accordance with the provisions of law, however, the company still has recommendations beyond its authority, requiring direction and resolution from the Provincial People's Committee.
Specifically, regarding the cost of moving the factory to temporary production on the remaining land, the District People's Committee has issued a decision approving the dismantling and relocation plan to support the company with a total amount of more than 309 million VND. All the dismantled and relocated assets that the company has arranged and stored cannot be installed at the temporary production location because the production line and equipment are too large for the land plot.
Instead, at the temporary production site, the company has invested in a production line, concrete yard, workshop and some auxiliary items with a total cost of about 3.8 billion VND. Therefore, Vinh Linh District People's Committee proposed that the Provincial People's Committee, departments and branches agree on the policy of 100% support for the items that the company has invested in.
Regarding the plan to complete the infrastructure at the new factory construction site, the District People's Committee has developed a plan with a total estimated cost of about 15 billion VND and proposed that the Provincial People's Committee agree to support the enterprise to continue production and business.
Regarding the cost of land acquisition for the additional land plot of 4,000 m2 expected to be recovered to lease to the company, the District People's Committee proposed to use the expressway project's budget to carry out compensation and support. At the same time, it proposed that departments and branches provide guidance on conditions for supporting the company's employees' severance allowance regime.
At the meeting, Vinh Linh District People's Committee also proposed to remove obstacles for 18 households arising during the implementation of compensation, support and resettlement work on the National Highway 9D overpass, the Van Ninh - Cam Lo section project.
Specifically, there are 3 cases of residential land with houses partially affected and the remaining part is within the road safety corridor; 6 households have not agreed to the compensation and support plan because the land acquisition stakes are close to houses and businesses, and the houses are higher or lower than the road surface when completed (the urban section does not have a traffic safety corridor); 9 households have received compensation and support but have not yet received land acquisition because the houses are higher or lower than the design elevation. The total amount of compensation and support proposed for these 18 households is 21.5 billion VND.
After listening to the opinions of representatives of Quang Tri Forestry Joint Stock Company and related departments and branches, concluding the working session, Permanent Vice Chairman of the Provincial People's Committee Ha Sy Dong highly appreciated the sense of responsibility of Vinh Linh district and related departments and branches in site clearance work to implement the project.
At the same time, severely criticized Quang Tri Forest Products Joint Stock Company for not actively cooperating with Vinh Linh district, leading to a prolonged time for site clearance for the company's area.
Basically agreeing with the proposals of Vinh Linh district at the working session, the Standing Vice Chairman of the Provincial People's Committee requested the Vinh Linh District People's Committee to complete the leveling of the land to ensure flatness for the area granted to the company. Speed up the progress of land acquisition and site clearance for the area additionally granted by the Provincial People's Committee.
Agree on the policy to allow Quang Tri Forestry Products Joint Stock Company to use the adjacent land for temporary production. Request Vinh Linh district to calculate the cost of dismantling and reinstalling so that the company can maintain production.
Regarding the funding to support temporary production enterprises, Vinh Linh district will evaluate specifically and accurately and submit it to the Provincial People's Committee for approval. Note that Vinh Linh district must calculate specifically, ensuring harmony of interests between the locality and enterprises and must comply with legal regulations.
Regarding support for workers, since this is a case of interruption due to relocation, according to regulations, 6 months of salary support is allowed. Therefore, the company is required to urgently prepare a budget and submit it to the District People's Committee for appraisal to have a basis for payment.
Regarding the problems of 18 households, the Provincial People's Committee will send a document to the Ho Chi Minh Road Project Management Board and relevant departments and branches requesting immediate implementation of procedures, striving to complete them by the end of November 2024 to carry out the payment work.
Le An
Source: https://baoquangtri.vn/giai-quyet-vuong-mac-trong-giai-phong-mat-bang-doi-voi-cong-ty-co-phan-lam-san-quang-tri-189287.htm