Many infrastructure projects have not been relocated yet.
According to Giao thong Newspaper, at the intersection of provincial road 623B through Nghia Ky commune (Tu Nghia), the first section of the project, the contractor is actively constructing the overpass abutment and roadbed to ensure the plan for launching the beams soon, speeding up the progress of each item.
The system of power lines, telecommunication cables, and public lighting is still located right next to the edge of the overpass on Provincial Road 623B.
However, next to it, the 0.4kV power line and public lighting line are still blocking the road despite the fact that nearly 2 years have passed and the investor and contractor have repeatedly requested Quang Ngai province to urgently relocate them.
Many workers constructing the iron and concrete sections of the bridge said they were concerned that electrical short circuits could cause fires and electric shocks, especially in the residential electrical wiring system and the tangled telecommunication cables hanging overhead... because the distance between the construction site and the power line is less than 3m.
Not far away, at the intersection of the road to Truong Oi, the 0.4kV power grid infrastructure system has long been part of the relocation plan of Quang Ngai province but is still in a state of waiting. Meanwhile, the roadbed on the southern side of the route has been filled with soil by the contractor to a height of about 2m. Below the existing roadbed, the clean water supply pipeline is also "dormant".
In fact, although the locality has actively participated in site clearance and basically handed over the main route to the contractor, there are still many obstacles along the route that hinder the project's construction and overall progress.
22kV power line across the construction site of a key national project.
A representative of the contractor Dacinco said that in order to complete the embankment of the first section of the route, a new road to Truong Oi on the west side of the project had to be constructed. However, the households whose land was confiscated, although they had handed over the land, were preventing the construction because they believed that the houses that had been cut down had not been granted land use right certificates by the competent authority.
"Due to the above problems, the work of stripping weathering and filling the main highway and the road to Truong Oi is still at a standstill. Due to technical infrastructure problems, the project's construction has been interrupted and discontinuous.
We hope that the locality will pay attention to supporting the contractor to remove difficulties in technical infrastructure to speed up progress according to project requirements," the contractor representative suggested.
Along the main route of the project through the XL1 package, there are scattered images of 22kV and 0.4kV power lines and telecommunication cable systems still existing within the construction area. The entangled locations have become major barriers for the contractor during the project implementation process, such as the section through Hanh Thuan and Hanh Minh communes (Nghia Hanh).
Similarly, the section through the XL2 and XL3 packages in Mo Duc district and Duc Pho town also encountered problems with the power grid infrastructure. Due to the problems, the earthworks and construction of related items were greatly affected.
Urgently relocate technical infrastructure and hand over the site
The representative of the Deo Ca contractor said that the main route of the project has basically been handed over by Quang Ngai province for the units to start construction. However, specific problems on the route such as power lines, fiber optic cables, water supply, etc. have caused the construction work to be intermittent.
Quang Ngai province directed relevant agencies to urgently relocate technical infrastructure works and hand over the site to the construction contractor.
We hope that the local commitments will be properly implemented, to hand over the entire site to the contractor this year, as a basis for completing the remaining items of the roadbed, speeding up the project progress to ensure the goal of completing the project as launched by the Prime Minister at the peak of "500 days and nights competing to complete 3,000km of expressway".
The representative of Project Management Board 2 said that the entire route has been surveyed and evaluated in terms of the ground. The main problem currently is the power grid system crossing the main route and the technical infrastructure with 6 major bottlenecks that need to be relocated soon. In addition, there are additional GPMB locations after adjustment, but so far the localities have not approved the compensation unit price because there is no land price list, leading to discontinuous construction work.
Regarding the power line system that has not been relocated, a representative of Quang Ngai Power Company said that the delay in relocation is due to the local government and the unit responsible for site clearance not being able to arrange the site for relocation. These units must arrange the site and determine the location for relocation before the electricity industry can start relocating the pole and power line system.
Director of the Provincial Traffic Construction Investment Project Management Board Ngo Van Dung said that with some remaining technical infrastructure problems on the main route, the Board has been coordinating with the investor to adjust the additional design to have a relocation location.
In the coming time, the unit will continue to coordinate with relevant units and localities to soon relocate electric poles, low-voltage wires as well as clean water supply systems out of the main route to ensure the site for the investor to carry out construction.
Quang Ngai electricity industry said the delay in relocating the power grid was due to the localities not yet handing over the pier sites.
At a recent working session with agencies to speed up the disbursement of investment capital for key projects, Vice Chairman of Quang Ngai Provincial People's Committee Tran Hoang Tuan requested relevant units and localities to coordinate to speed up the relocation of technical infrastructure so that the construction unit can carry out the construction on schedule. Do not let site problems affect the national key project.
Source: https://www.baogiaothong.vn/gan-2-nam-thi-cong-cao-toc-quang-ngai-hoai-nhon-van-vuong-mat-bang-192241022170233658.htm
Comment (0)