The 1,200 billion VND coastal road connecting Lien Chieu port is still stuck in land acquisition issues.
The coastal road project connecting Lien Chieu port has a total investment capital of over 1,200 billion VND, of which over 500 billion has been disbursed so far. However, the project is still stuck in site clearance.
According to the Management Board of Priority Infrastructure Investment Projects in Da Nang, as of September 14, the Coastal Road project connecting Lien Chieu Port has disbursed more than VND558 billion, reaching 46% of the total investment of the project of VND1,203 billion.
The capital plan for 2024 is 271 billion VND, of which more than 148 billion VND has been disbursed; of which, the central budget capital is more than 125 billion VND, the city budget capital is more than 22 billion VND.
According to the Management Board, the project is being implemented on schedule, however there are still some cases where the site has not been handed over for construction.
To ensure the progress of construction and disbursement of the 2024 capital plan, 246 billion VND has been allocated for construction and installation. The Management Board has coordinated with units to speed up site clearance work.
The coastal road project connecting Lien Chieu port is under construction. |
To date, 240/255 files have been handed over and 287/291 graves have been relocated. However, there are still 15 files that have not been handed over and 4 graves. In addition, there are 15 files related to the drainage canal in Hoa Khanh Industrial Park...
To ensure the land for the construction of the Coastal Road Project connecting Lien Chieu Port, the Management Board of Priority Infrastructure Investment Projects in Da Nang requested Lien Chieu District to promptly complete compensation and clearance procedures and mobilize households to hand over the land.
The coastal road project connecting Lien Chieu port has a total investment of more than 1,203 billion VND; of which the central budget is 500 billion VND, the rest is from Da Nang city budget. The project is expected to be completed and put into use in 2025.
The coastal road project connecting Lien Chieu port is about 2,963km long; including 6 lanes.
The project will build different-level overpasses at the intersection of the North-South railway and Nguyen Van Cu street (QL1A), different-level overpasses at the intersection of the end of the route with the southern bypass of Hai Van - Tuy Loan road tunnel to ensure that traffic flows into and out of the port are independent and do not intersect when passing through the intersection; build a bridge over the canal according to the plan and build a new Lien Chieu bridge; build an underpass to Luong stream and an internal underpass for Lien Chieu Industrial Park...