Accordingly, the project is expected to be constructed from March 31, 2025 to March 31, 2026. The provincial transport construction investment project management board requires the contractor to ensure traffic safety during the construction process, not cause environmental pollution, and be responsible for overcoming incidents caused by the construction process to neighboring works and houses in the area...
According to the design, the project has a length of 4.7km with a design speed of 50km/h, a road width of 27m with 4 lanes and sidewalks. This project implements a rainwater drainage system with a newly built longitudinal sewer system (replacing the old degraded sewer system that does not ensure drainage capacity for the area), designed to be located under the road close to the curb.
Surface water is collected directly from the road surface at the intakes into the longitudinal sewer system and discharged into the existing canal locations at Quan bridge and through the sewer systems on traffic routes in accordance with the planning and overall flood prevention project of Tay Ninh city and Hoa Thanh town (Hoang Le Kha, Nguyen Trai, Lac Long Quan streets...).
The project to renovate Cach Mang Thang Tam Street, in addition to beautifying the appearance of an important road in Tay Ninh city and creating urban beauty, is also expected to solve the problem of localized flooding after each heavy rain, which has affected traffic and the lives of people on both sides of the road for many years.
Tan Hung
Source: https://baotayninh.vn/du-an-chinh-trang-duong-cach-mang-thang-tam-thoi-gian-thi-cong-du-kien-365-ngay-a188358.html
Comment (0)