At the second conference to summarize the 30-day and night campaign, units in Dong Nai province said that the section through Bien Hoa city had handed over nearly 20ha/60ha to the investor, and the section through Long Thanh district had handed over about 56ha/230ha.
Regarding the area of land inventory, Bien Hoa City People's Committee and Long Thanh District People's Committee said that the agencies that have conducted the land inventory for compensation in the Bien Hoa - Vung Tau expressway project have basically completed 100%.
Localities continue to urgently approve compensation plans, support people, and disburse investment capital.
However, in each locality there are still hundreds of cases where land origin verification has not been completed.
Explaining the problems affecting progress, localities said that there were many cases of houses and properties built on other people's land, so according to regulations, they had to declare the owner and complete the documents, which took a lot of time in setting prices and making compensation plans.
In addition, there are many plots of land that overlap the recovered boundaries with high-voltage power projects, so it is necessary to ask for opinions on compensation and support plans... Therefore, it significantly affects the progress of project implementation.
Mr. Vo Tan Duc, acting chairman of Dong Nai Provincial People's Committee, assessed that the inventory and confirmation of land origin were difficult tasks for the project, but local departments and branches worked day and night to clear the project's site.
However, the goal of handing over the entire project site before June 30 could not be achieved.
Therefore, localities are making efforts and focusing human resources to complete the goal of handing over the entire site for project construction in July 2024.
"To do this, sectors and localities must complete the approval of compensation and support plans for all remaining cases and the resettlement review for households," Mr. Duc emphasized.
The Bien Hoa - Vung Tau expressway section through Dong Nai is more than 34km long.
The Bien Hoa - Vung Tau expressway construction investment project runs about 34.2km through Dong Nai province (6.2km through Bien Hoa city and 28km through Long Thanh district).
In which, component project 1 (passing through Bien Hoa city and Long Thanh district, invested by Dong Nai province People's Committee) has a length of 16km, requiring the recovery of over 137 hectares of land.
In component project 2, the length is about 18.2km (with the Ministry of Transport as the managing agency), with a total land acquisition area of over 151.5ha.
Source: https://tuoitre.vn/du-an-cao-toc-bien-hoa-vung-tau-qua-dong-nai-moi-giao-gan-80ha-mat-bang-thi-cong-20240629185740255.htm