How is the Quang Tri Airport project being constructed?

Báo Giao thôngBáo Giao thông15/01/2025

Quang Tri Airport Project is constructing the apron and material curb, continuing to implement site clearance of the remaining 25.73 hectares, including 6.74 hectares of the project core area.


Cleared more than 239.6 hectares of land

On January 15, Mr. Nguyen Long Hai - Secretary of Quang Tri Provincial Party Committee conducted a field survey of Quang Tri Airport project and worked with the Standing Committee of Gio Linh District Party Committee to listen to reports on socio-economic development, national defense and security, Party building work, political system in 2024, and key tasks in 2025.

Dự án Cảng hàng không Quảng Trị đang thi công thế nào?- Ảnh 1.

Mr. Nguyen Long Hai - Secretary of Quang Tri Provincial Party Committee (standing in the middle wearing a blue jacket) inspects the Quang Tri Airport project.

Regarding the site clearance work of Quang Tri Airport project - part of component project 1, according to Gio Linh district's report, to date, the site clearance has been completed for more than 239.6 hectares (core area of ​​more than 128.8 hectares) out of a total area of ​​265.37 hectares; 140.5 hectares of cleared land has been handed over to the investor.

For the remaining 25.73 hectares that have not been cleared, the District People's Committee has basically completed the assignment of ownership and pricing; at the same time, actively propagandizing and mobilizing affected households to agree to relocate tombs and temporary residence before completing resettlement areas and cemeteries.

Quang Tri Provincial People's Committee has also directed Gio Linh District People's Committee to develop a specific implementation plan for each work item to soon complete site clearance, in which priority is given to site clearance for 6.74 hectares of core area to hand over to investors in February 2025.

Regarding component project 2 - Airport construction, with a total investment of VND 5,821 billion, the contractor is currently implementing the construction of the parking lot and material curb; other items are being submitted for technical design appraisal.

Early completion of resettlement projects

Notably, the Quang Tri Airport project has 35 affected households subject to resettlement; 97 mausoleums and 640 graves must be relocated. The resettlement areas and cemeteries serving the site clearance have not been implemented yet, and the economic and technical reports are currently being adjusted.

The locality has mobilized 3 households to temporarily relocate within the runway area to hand over to the project enterprise for construction, and at the same time mobilized people to relocate about 50% of the above tombs.

Dự án Cảng hàng không Quảng Trị đang thi công thế nào?- Ảnh 2.

A corner of Quang Tri Airport project under construction.

At the meeting, leaders of the People's Committee of Quang Tri province and Gio Linh district raised a number of difficulties and obstacles in the project's site clearance process.

In particular, the progress of land acquisition and clearance depends on the completion time of resettlement areas for households and cemeteries to relocate affected tombs. However, currently the resettlement areas and cemeteries have not been completed, and the affected cases do not agree to relocate and hand over the site.

Meanwhile, the procedures for building a cemetery and housing resettlement area take a lot of time; according to the new regulations, the time to publicize the compensation, support and resettlement plan is 30 days, which significantly affects the progress of site clearance.

At the meeting, Mr. Nguyen Long Hai - Secretary of Quang Tri Provincial Party Committee acknowledged and highly appreciated the efforts of Gio Linh district in leading and directing the implementation of socio-economic development tasks as well as site clearance work for key projects in the area in recent times...

Dự án Cảng hàng không Quảng Trị đang thi công thế nào?- Ảnh 3.

Quang Tri Airport project started construction on July 6, 2024.

Regarding the Quang Tri Airport project, the Secretary of the Quang Tri Provincial Party Committee requested Gio Linh district to focus on accelerating the site clearance work for the remaining area and determine specific completion milestones. Accelerate the completion of resettlement projects; have a plan for temporary residence to ensure the site clearance progress and hand over the clean site to the investor.

In addition, the People's Committee of Quang Tri province and relevant departments and branches reviewed and approved the contractor selection plan so that Gio Linh district could soon complete resettlement projects...

The Quang Tri Airport construction investment project has been approved by the Prime Minister in principle for investment and construction under the public-private partnership (PPP) method and the Quang Tri Provincial People's Committee has approved the feasibility study report.

The project aims to meet the increasing demand for air transport, contributing to promoting political, economic and social development; at the same time ensuring high mobility in defense as well as in rescue work; ensuring national defense and security of the Central region in general and Quang Tri province in particular; in line with the planning and orientation of transport development.

The project is implemented in Gio Quang, Gio Hai and Gio Mai communes of Gio Linh district with a scale of more than 265 hectares, a total investment of more than 5,800 billion VND; built to meet the standards of a level 4C airport (according to the classification of the International Civil Aviation Organization - ICAO); capable of developing for code E aircraft operations; allowing the operation of irregular international flights according to the planning in Decision 648 dated June 7, 2023 of the Prime Minister (when needed) and a level II military airport, meeting the needs of operating up to 5 million passengers/year and 25,500 tons of cargo/year.

The project implementation period is 50 years, of which the project preparation and construction investment period is 24 months; the operation and toll collection period for capital recovery is more than 47 years and 2 months.

The Quang Tri Airport construction investment project includes component project 1 (land acquisition and construction of state agencies at the airport) implemented in the form of public investment, and component project 2 (Airport construction) implemented in the form of public-private partnership (PPP), Build-Operate-Transfer (BOT) contract.

The Quang Tri Airport Land Acquisition Project (Phase 1) has had its feasibility study report approved by the Quang Tri Provincial People's Committee in December 2023.

Accordingly, the total area of ​​the project in Gio Quang, Gio Mai and Gio Hai communes of Gio Linh district is over 265.3 hectares, of which the common land is over 177.6 hectares, the civil airport land is over 87.7 hectares (the military land area of ​​51.2 hectares has not been implemented yet). The total investment is over 233.1 billion VND, with the People's Committee of Gio Linh district as the investor.

Component project 2 - Construction of the airport under the Quang Tri Airport construction investment project was held by the consortium of T&T Transport Infrastructure Investment and Development Company Limited - CIENCO4 Group Joint Stock Company in coordination with the People's Committee of Quang Tri province on July 6, 2024.



Source: https://www.baogiaothong.vn/du-an-cang-hang-khong-quang-tri-dang-thi-cong-the-nao-192250115170221001.htm

Comment (0)

No data
No data

Same tag

Same category

Same author

Figure

The movie that shocked the world announced its screening schedule in Vietnam
Brilliant red leaves in Lam Dong, curious tourists travel hundreds of kilometers to check-in
Binh Dinh fishermen with '5 boats and 7 nets' busily exploit sea shrimp
Foreign newspapers praise Vietnam's 'Ha Long Bay on land'

No videos available