"Miracle" in infrastructure investment
The conference was held directly at the Vietnam Electricity Group (Hanoi) bridge, online to the bridge points of 9 provinces and cities that the line passes through (Hung Yen, Hai Duong, Thai Binh, Nam Dinh, Ninh Binh, Thanh Hoa, Nghe An, Ha Tinh, Quang Binh) and the bridge points of 63 electricity companies nationwide.
At the Conference, the leader of Vietnam Electricity Group (EVN) informed that the 500kV Power Transmission Line Project, Circuit 3, Quang Trach - Pho Noi (500kV Transmission Line Project, Circuit 3) was assigned by EVN to the National Power Transmission Corporation (EVNNPT) as the investor, with a total length of 519 km, 1,177 pole locations, 513 anchorages, passing through 211 communes/wards of 43 districts in 9 provinces with a total investment of more than 22,300 billion VND. This is a key, urgent project, of great significance to improve the stability of the power system operation, increase power supply to the North in 2024 and the following years, contributing to ensuring national energy security. Under the strong and close direction of the Government and the Prime Minister, and the attention and support of ministries, branches, localities and people, EVN/EVNNPT has determined and made efforts to complete the energization of the 500kV Circuit 3 Transmission Line Projects after more than 6 months of construction instead of 3-4 years as usual.
The completion of the project with a huge amount of work, involving many ministries, branches, localities and many households, in a short period of time in history has left many valuable lessons not only for the electricity industry but also for the country's large projects and works in the coming time, especially in implementing investment procedures; converting land and forest use purposes; site clearance; purchasing materials and equipment; mobilizing means, forces, and organizing construction...
In particular, the time for preparing and submitting the investment policy/adjusting the investment policy was only nearly 5 months. This is a record short time compared to projects of similar scale and the time has been shortened by 1.5 - 2 years. The project spans 9 provinces, with a compensation and site clearance area of about 183 hectares, 5,248 households and 96 organizations, achieving record progress contributing to the success of the projects.
In particular, in just 6 months of construction, with the efforts of EVN/EVNNPT, contractors and supporting forces, 2.54 million m3 of earth and rock excavation were completed; 705 thousand m3 of concrete of all kinds were poured; 69.8 thousand tons of foundation reinforcement were processed; 1,177 steel columns were erected with a total weight of 139,000 tons; and 13,983 km of various types of wire were stretched.
At the Conference, the opinions of leaders of ministries, branches and localities all agreed that the "miracle" in infrastructure investment and construction as mentioned above was thanks to the attention and drastic direction of the Prime Minister, Deputy Prime Ministers, leaders of many ministries and branches and the participation of local authorities and people. The management, operation and implementation were drastic, scientific and creative; the mobilization and efforts, joint efforts and hearts of the entire political system, forces participating in construction, mass mobilization and propaganda work, especially the close adherence, drastic and timely removal of difficulties and obstacles arising in the process of project implementation...
Many lessons learned
The 500 kV circuit 3 Quang Trach - Pho Noi project has been put into operation with special significance in many aspects of economy, politics, society, security - defense. In particular, the project has strategic significance in contributing to ensuring electricity supply in the North in particular and national energy security in general. The project has the meaning of connecting the economy, linking regions; connecting widely, synchronously, improving the efficiency of exploiting national power transmission systems...
Speaking at the Conference, Prime Minister Pham Minh Chinh expressed his emotion at the growth and maturity of the electricity industry, with high growth, no incidents or power shortages to meet the country's development requirements; through the power supply and the success of the 500 kV line project, the image of electricians has been enhanced in the hearts of the people.
Emphasizing the special significance of the Project for the country's energy security, on behalf of the Government, Prime Minister Pham Minh Chinh respectfully thanked, acknowledged and highly appreciated the efforts, endeavors, and joint efforts of officials, employees and workers in the electricity sector; Party committees, authorities at all levels and people where the power line passes through; the Fatherland Front, the Public Security Forces, the Army, socio-political organizations such as the Vietnam General Confederation of Labor, the Youth Union, the Women's Union, the Veterans Association; news agencies, newspapers; businesses and related entities.
Talking about the significance of the success of the 500kV line 3 project, the Prime Minister affirmed: Nothing is impossible if there is determination, dare to think, dare to do, know how to do. The project contributes to enhancing the role, position, and prestige of the Electricity industry in the hearts of the people and domestic and foreign enterprises; contributes to strengthening confidence, courage, intelligence, and creativity; learns from experience while doing, gradually expands, not perfectionist, not hasty.
Regarding lessons learned, the Prime Minister said that the success of the Project is due to knowing how to promote the strength of national solidarity; mobilizing the strength of the entire political system; ensuring the leadership of the Party, with the viewpoint that resources originate from thinking and vision, motivation originates from innovation and creativity, strength originates from the people and businesses. At the same time, promptly remove institutional obstacles; ideology must be clear, determination must be high, efforts must be great, actions must be drastic, work must be focused, key points, and each job must be completed. Along with that is the clear assignment of people, work, time, results, and products, coupled with increased supervision and inspection, ensuring progress, ensuring quality, technical and aesthetic works, not increasing prices, fighting negativity and waste...
The Prime Minister requested to continue to restore; finalize accounts, complete documents, and accept the project; continue to care for the lives of people who have given up land for the project; and have forms of rewards for collectives and individuals with outstanding achievements and contributions to the project.