TPO - The overpass project of the Tran Quoc Hoan - Cong Hoa connecting road project (connecting T3 terminal - Tan Son Nhat International Airport) has been completed and is ready to open to traffic next April.
TPO - The overpass project of the Tran Quoc Hoan - Cong Hoa connecting road project (connecting T3 terminal - Tan Son Nhat International Airport) has been completed and is ready to open to traffic next April.
The Tran Quoc Hoan - Cong Hoa connecting road project (Tan Binh district, Ho Chi Minh City) is a key traffic project connecting with Terminal T3 - Tan Son Nhat International Airport. |
The project has a total investment of more than 4,800 billion VND, is about 4 km long, and includes the construction of branch roads, overpasses and tunnels. In the photo is the overpass (overpass) in front of the T3 terminal area. |
The overpass (elevated overpass) is nearly 1km long, starting from the Tran Quoc Hoan - Cong Hoa connecting road, intersecting with Highway 18E and ending at Hoang Hoa Tham intersection. |
This project connects directly to terminal T3. Photo: AX |
The overpass is 17m wide and is designed with 4 lanes (2 lanes in each direction). |
Currently, the overpass project has been completed, items such as asphalt carpet, guide lines, lighting, and railings have all been completed and are ready to open to traffic next April. |
The viaduct in front of terminal T3. |
Up to now, the 1.25 km long connecting road (from Phan Thuc Duyen underpass to Hoang Hoa Tham street) has been completed and put into operation. |
According to the HCMC Department of Transport (investor), the 4-lane overpass in front of T3 terminal has been completed. |
Currently, the remaining part of the route connecting Tran Quoc Hoan - Cong Hoa (from Hoang Hoa Tham Street to Truong Chinh Street) is under urgent construction. |
The total progress of the Tran Quoc Hoan - Cong Hoa connecting road project is currently about 95%. Currently, the units are urgently completing package No. 13 (including construction of roads, retaining walls, sidewalks, drainage, traffic organization at the end of the route and expansion of Truong Chinh Street). |
The investor said that the total progress of package 13 is about 80%. After Tan Binh district handed over the entire site at the end of February, the project is continuing to complete the remaining items. |
“It is expected that the entire route connecting Tran Quoc Hoan - Cong Hoa will be put into operation in April. It will be synchronized with the opening of Terminal T3 - Tan Son Nhat International Airport on April 30 this year,” said a representative of the Ho Chi Minh City Department of Transport. |
Source: https://tienphong.vn/dien-mao-cau-vuot-ket-noi-nha-ga-t3-san-bay-tan-son-nhat-sap-thong-xe-post1723027.tpo
Comment (0)