This morning, April 10, Deputy Minister of Transport Nguyen Xuan Sang and Vice Chairman of Quang Ninh Provincial People's Committee Bui Van Khang inspected the progress and resolved difficulties of the Van Ninh General Port project and maritime infrastructure in the area. They were accompanied by leaders of a number of relevant departments and sectors and the Mong Cai City People's Committee.
The Van Ninh General Port Project is invested and built on an area of 82.79 hectares, in Van Ninh commune, Mong Cai city, with a total investment of over 2,248 billion VND in phase 1, invested by Van Ninh International Port Joint Stock Company. The investment and construction period is expected to be 3 years, completed and put into operation in the fourth quarter of 2024.
The port is designed with a main wharf of 500m long, which can simultaneously dock 2 ships of up to 20,000 DWT or 3 ships of 10,000 DWT and dock barges at the back. The warehouse area will be invested synchronously, equipped with modern infrastructure to best meet the requirements of handling general cargo and containers...
Along with the implementation of procedures for assessing detailed technical drawings of the port surface items, the investor and the contractor are implementing dredging and leveling the port. In particular, dredging the water area in front of the port, pumping sand into the geotechnical pipe of the project surrounding dike has reached 55%; dredging and leveling the project's beach foundation has reached nearly 30% of the volume. The implementation of the construction is facing difficulties mainly related to the lack of leveling materials...
Based on the on-site inspection and difficulties of the project, Deputy Minister of Transport Nguyen Xuan Sang requested the departments and divisions under the Ministry to support the investor to urgently complete the procedures for approving the project's design and construction drawings; guide the 6-12 Van Don Veteran Entrepreneurs Company Limited to complete the procedures for dredging the level -7 channel to serve the filling of the Van Ninh Port project.
Directly directing the inspection session, Vice Chairman of the Provincial People's Committee Bui Van Khang requested the Department of Natural Resources and Environment to complete procedures related to the land mine in Village 5, Quang Nghia Commune, Mong Cai City, to serve the construction of the road connecting Van Don - Mong Cai Expressway to Van Ninh Port, the section constructed by the investor; at the same time, Mong Cai City urgently completes the construction progress of the road section invested by the province.
Regarding the project construction, the Vice Chairman of the Provincial People's Committee and the Deputy Minister of Transport agreed to request the project investor to increase human resources and equipment for construction items with construction design drawings; especially the construction of the project's foundation and yard to ensure that they exceed the tidal peak to serve the storage of other materials. At the same time, the investor needs to urgently mobilize the floating construction rig to organize test drilling of the port embankment piles to complete the experiment and perform the construction simultaneously. Based on the removal of difficulties of the Ministry and the province, the investor needs to speed up construction and strive to complete the project ahead of schedule to anticipate the recovery, trends in transportation and logistics activities.